XYZ Company provided the following information regarding Product XY: Direct material costs OMR3 per unit of product; Direct labor costs OMR5 per direct labor hour; Predetermined overhead rate OMR10 per direct labor hour. The cost of a job for 550 units of product XY, which uses a total of 170 direct labor hours, is: Select one:
a. OMR4,200
b. None of the answers given
c. OMR9,900
d. OMR6,100
e. OMR4,050
Answer is a. OMR4,200
Explanation:
Calculation of cost of job :
Direct material cost per unit = OMR3
Total number of units = 550 units
Total direct material cost = OMR3 x 550 = OMR1650
Direct labor cost per direct labor hour = OMR5
Total direct labor hours = 170
Total direct labor cost = OMR5 x 170 = OMR850
Predetermined overhead rate = OMR10 per direct labor hour
Total direct labor hours = 170
Total overhead cost = OMR10 x 170 = OMR1700
Total cost of job =
Total direct material cost + Total direct labor cost + Total overhead cost
= OMR1650 + OMR850 + OMR1700 = OMR4200