Parallel Enterprises has collected the following data on one of its products. During the period the company produced 25,000 units. The direct materials quantity variance is?
Direct materals standard (7kg. @ $2/kg): $14 per finished unit
Actual cost of materials purchased: $322,500
Actual direct materials purchased and used: 150,000 kg
Standard Direct Material Cost = $2 per kg
Actual Direct Materials Quantity = 150,000 kg
Standard Direct Materials Quantity = Number of units produced *
Standard direct material per unit
Standard Direct Materials Quantity = 25,000 * 7 kg
Standard Direct Materials Quantity = 175,000 kg
Direct Materials Quantity Variance = Standard Direct Material
Cost * (Actual Direct Materials Quantity - Standard Direct
Materials Quantity)
Direct Materials Quantity Variance = $2.00 * (150,000 -
175,000)
Direct Materials Quantity Variance = $50,000 Favorable