Pardun Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:
Pardun Corporation's management keeps track of the time it takes
to process orders. During the most recent month, the following
average times were recorded per order:
Days | |
Wait time | 13.2 |
Inspection time | 0.7 |
Process time | 1.60 |
Move time | 0.6 |
Queue time | 2.2 |
Required:
a. Compute the throughput time.(Enter your answer rounded to 1 decimal places.)
b. Compute the manufacturing cycle efficiency (MCE). (Enter your answer rounded to 2 decimal places.)
c. What percentage of the production time is spent in non-value-added activities?
d. Compute the delivery cycle time. (Round your answer to 1 decimal place.)
a. Throughput time = Process time + Inspection time + Move time + Queue time
= 1.60 days + 0.7 days + 0.6 days + 2.2 days = 5.1 days
b. MCE = Value-added time (Process time) / Throughput time
= 1.60 days / 5.1 days = 0.31
c. Percentage of time spent on non-value-added activities
= 100% - MCE% = 100% - 31% = 69%
d. Delivery cycle time = Wait time + Throughput time
= 13.2 days + 5.1 days = 18.3 days