Fey Company’s organization chart includes the president; the vice president of production; three assembly plants—Dallas, Atlanta, and Tucson; and two departments within each plant—Machining and Finishing. Budget and actual manufacturing cost data for July 2017 are as follows.
Finishing Department—Dallas: direct materials $41,050
actual, $44,680 budget; direct labor $83,110 actual, $83,870
budget; manufacturing overhead $52,120 actual, $51,130
budget.
Machining Department—Dallas: total manufacturing
costs $220,130 actual, $216,870 budget.
Atlanta Plant: total manufacturing costs $424,810 actual,
$422,130 budget.
Tucson Plant: total manufacturing costs $494,840 actual,
$496,570 budget.
The Dallas plant manager’s office costs were $96,120 actual and
$93,480 budget. The vice president of production’s office costs
were $134,790 actual and $132,090 budget. Office costs are not
allocated to departments and plants.
Prepare the reports in a responsibility system for: The plant manager—Dallas. (List departments in alphabetical order, e.g. Finishing, Machining.)
Prepare the reports in a responsibility system for: The vice president of production. (List assembly plans in alphabetical order, e.g. Atlanta, Dallas.)