Myers Company uses a flexible budget for manufacturing overhead
based on direct labor hours. Variable manufacturing overhead costs
per direct labor hour are as follows:
Indirect labor $1.00
Indirect materials 0.70
Utilities 0.20
Fixed overhead costs per month are Supervision $4,100, Depreciation
$1,900, and Property Taxes $700. The company believes it will
normally operate in a range of 7,300–10,900 direct labor hours per
month.
Prepare a monthly manufacturing overhead flexible budget for 2017
for the expected range of activity, using increments of 1,200
direct labor hours. (List variable costs before fixed
costs.)
MYERS COMPANY
Monthly Manufacturing Overhead Flexible Budget
For the Year 2017
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
$
[Entry field with correct answer]
$
[Entry field with incorrect answer]
$
[Entry field with incorrect answer]
$
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with incorrect answer]
[Entry field with incorrect answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
[Entry field with correct answer]
Activity Level
Depreciation
Direct Labor Hours
Fixed Costs
Indirect Labor
Indirect Materials
Property Taxes
Supervision
Total Costs
Total Fixed Costs
Total Variable Costs
Utilities
Variable Costs
$
[Entry field with correct answer]
$
[Entry field with incorrect answer]
$
[Entry field with incorrect answer]
$
[Entry field with correct answer]
Flexible | Budget | ||||||
direct labor hours | 7,300 | 8,500 | 9,700 | 10,900 | |||
variable costs | |||||||
Indirect labor | 1 | 7300 | 8500 | 9700 | 10900 | ||
indirect materials | 0.7 | 5110 | 5950 | 6790 | 7630 | ||
utilities | 0.2 | 1460 | 1700 | 1940 | 2180 | ||
total variable costs | 1.9 | 13870 | 16150 | 18430 | 20710 | ||
fixed cost | |||||||
supervision | 4,100 | 4,100 | 4,100 | 4,100 | |||
Depreciation | 1,900 | 1,900 | 1,900 | 1,900 | |||
property taxes | 700 | 700 | 700 | 700 | |||
total fixed cost | 6,700 | 6,700 | 6,700 | 6,700 | |||
total cost | 20,570 | 22,850 | 25,130 | 27,410 | |||