Question

Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion....

Sallys construction. is a construction company and recognizes revenue, costs, and gross profit at project completion. At the start of Year 1, Kip enters a contract to build an office building for $100 million. The project is completed by the end of Year 2. The following additional information is available for this project (amounts in millions):

YEAR 1 YEAR 2

Costs incurred during each year

$20 $70

Costs expected in future

$60 0

sallys Year 2 revenue will be:

Homework Answers

Answer #1
Information Available Amount in Mn $
Total Cost of the Project                      100
Year 1 Year 2
Cost Incurred during each year 20 70
Cost Expected In Future 60 0
Computation of % of completion, revenue recognition (Amount in Mn $)
Year Actual cost incurred (A) Total cost incurred till date (B) Estimated Cost (B1) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price Total Revenue to be recoganized (F) (E * D) Revenue Reconginsed in Earlier Year
(G)
Revenue for current period (H= F-G)
(E)
Year 1 20 20 60 80 25.00%            100 25 0 25
Year 2 70 90 0 90 100.00% 100 100 25 75

Sallys Year 2 revenue will be: $ 75 Mn

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
A construction company entered into a fixed-price contract to build an office building for $12 million....
A construction company entered into a fixed-price contract to build an office building for $12 million. Construction costs incurred during the first year were $4 million and estimated costs to complete at the end of the year were $6 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract?
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2015 and completed in 2016. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $32 million of costs and estimates an additional $87 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $52 million and estimated...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $330 million. The expected completion date is April 1, 2020, just in time for the 2020 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): 2018 2019 2020 Costs incurred during the year $ 90 $ 70 $ 45 Estimated costs to complete as of...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to...
Georgia Co. began a construction project in 2021 with a contract price of $162 million to be received when the project is completed in 2023. During 2021, Georgia incurred $30 million of costs and estimates an additional $82 million of costs to complete the project. Georgia recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.    In 2022, Georgia incurred additional costs of $59 million and...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract Methods Halsey Building Company signed a contract to build an office building for $60,000,000. The scheduled construction costs follow. Year Cost 2016 $12,000,000 2017 18,000,000 2018 10,000,000 Total $40,000,000 The building is completed in 2018. For each year, compute the revenue, expense, and gross profit reported for this construction project using each of the following methods. a. Percentage-of-completion method 2016 2017 2018 Revenue $Answer $Answer $Answer Expense $Answer $Answer $Answer Gross Profit $Answer $Answer $Answer...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to...
Indiana Co. began a construction project in 2021 with a contract price of $165 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $65 million...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $30 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $50 million and estimated...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam...
Beavis Construction Company was the low bidder on a construction project to build an earthen dam for $1,800,000. The project was begun in 2012 and completed in 2013. Cost and other data are presented below: 2012 2013   Costs incurred during the year $ 450,000 $1,100,000      Estimated costs to complete 1,050,000 0      Billings during the year 400,000 1,400,000      Cash collections during the year 300,000 1,500,000    Assume that Beavis recognizes revenue on this contract over time according to...
Cinnabar Construction Company has consistently used the input method based on costs incurred to recognize revenue...
Cinnabar Construction Company has consistently used the input method based on costs incurred to recognize revenue from a performance obligation satisfied over time. During Year 1, Cinnabar entered into a fixed-price contract to construct an office building for $10 million. Information relating to the contract is as follows: December 31 Year 1 Year 2 Progress to completion 20% 60% Estimated total costs at completion $7,500,000 $8,000,000 Gross profit recognized (cumulative) 500,000 1,200,000 Contract costs incurred during Year 2 were A.$3,500,000...