The following information concerns production in the Baking Department for December. All direct materials are placed in process at the beginning of production.
ACCOUNT Work in Process—Baking Department | ACCOUNT NO. | ||||||||
Date | Item | Debit | Credit | Balance | |||||
Debit | Credit | ||||||||
Dec. | 1 | Bal., 6,600 units, 4/5 completed | 13,992 | ||||||
31 | Direct materials, 118,800 units | 190,080 | 204,072 | ||||||
31 | Direct labor | 53,360 | 257,432 | ||||||
31 | Factory overhead | 30,010 | 287,442 | ||||||
31 | Goods finished, 120,300 units | 276,426 | 11,016 | ||||||
31 | Bal., ? units, 4/5 completed | 11,016 |
a. Based on the above data, determine each cost listed below. Round "cost per equivalent unit" answers to the nearest cent.
1. Direct materials cost per equivalent unit. |
$ 1.60 |
2. Conversion cost per equivalent unit. |
$ 0.70 |
3. Cost of the beginning work in process completed during July. |
$ 14,916 |
4. Cost of units started and completed during July. |
$ 261,510 |
5. Cost of the ending work in process. |
$ 11,016 |
EUP - FIFO Method |
Units |
% Material |
EUP Materials |
% Conversion |
EUP - Conversion |
Units of ENDING WIP |
5,100 |
100.0% |
5,100 |
80.0% |
4,080 |
Units STARTED & COMPLETED |
113,700 |
100% |
113,700 |
100% |
113,700 |
Units of beginning WIP |
6,600 |
0.00% |
- |
20.00% |
1,320 |
Equivalent Units of Production |
118,800 |
119,100 |
|||
COST per EUP |
Material |
Conversion |
|||
Cost incurred this period |
$ 190,080.00 |
$ 83,370.00 |
|||
Total Costs |
Costs |
$ 190,080.00 |
Costs |
$ 83,370.00 |
|
Equivalent units of production |
EUP |
118,800 |
EUP |
119,100 |
|
Cost per EUP |
$ 1.60000 |
$ 0.7000 |
COST ASSIGNMENT & RECONCILIATION |
||||
Cost Transferred out: |
EUP |
Cost per EUP |
Total Cost |
|
Cost of Beginning WIP |
$ 13,992.00 |
|||
Cost to complete beginning WIP- |
||||
- Direct Materials |
- |
$ 1.60 |
$ - |
|
- Conversion |
1,320 |
$ 0.70 |
$ 924.00 |
|
Total cost to complete beginning WIP |
$ 14,916.00 |
|||
Cost of Units started & completed this period: |
EUP |
Cost per EUP |
Total Cost |
|
- Direct Materials |
113,700 |
$ 1.60 |
$ 181,920.00 |
|
- Conversion |
113,700 |
$ 0.70 |
$ 79,590.00 |
|
Total costs started & Completed this period |
$ 261,510.00 |
|||
Total cost of work finished this period |
$ 276,426.00 |
Get Answers For Free
Most questions answered within 1 hours.