During 2017 Nilsen company started a construction job with a
contract price of $2,400,000. The job...
During 2017 Nilsen company started a construction job with a
contract price of $2,400,000. The job was completed in 2019. the
following information was available 2017 2018 2019 cost incurred to
date $750,000 $1,540,000 $2,000,000. Estimated cost $1,250,000
$660,000 -0-. Customer billing to date $650,000 $1,750,000
$2,400,000. Cash collection to date $450,000, $1,250,000
$2,250,000. Calculate the estimated gross profit and revenue to be
recognized on this contract for the years ended december 31,
2017,2018 and 2019 assuming nilsen recognizes revenue...
Revenue Recognition
In 2017, Chicago Construction began work on a three-year
construction project to build a...
Revenue Recognition
In 2017, Chicago Construction began work on a three-year
construction project to build a new performing arts complex (the
"PAC"). Chicago uses the percentage-of-completion method of
accounting. At the end of 2017, the company completed 25% of the
project. The following financial statement information indicates
the results to date for the PAC at the end of 2017:
Actual Cost incurred in 2017 $35 million
Construction in progress (as of
12/31/2017) $50
million
Accounts Receivable from construction billings (as...
Curtiss Construction Company, Inc., entered into a fixed-price
contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price
contract with Axelrod Associates on July 1, 2018, to construct a
four-story office building. At that time, Curtiss estimated that it
would take between two and three years to complete the project. The
total contract price for construction of the building is
$4,540,000. Curtiss concludes that the contract does not qualify
for revenue recognition over time. The building was completed on
December 31, 2020. Estimated percentage of completion, accumulated
contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price
contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price
contract with Axelrod Associates on July 1, 2018, to construct a
four-story office building. At that time, Curtiss estimated that it
would take between two and three years to complete the project. The
total contract price for construction of the building is
$4,540,000. Curtiss concludes that the contract does not qualify
for revenue recognition over time. The building was completed on
December 31, 2020. Estimated percentage of completion, accumulated
contract costs incurred,...
McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun...
McCombs Contractors received a contract to construct a mental
health facility for $2,500. Construction was begun in 2017 and
completed in 2018. Cost and other data are presented below:
2017
2018
Costs incurred during the
year
$1,500
$1,300
Estimated costs to
complete
1,200
0
Billings during the
year
1,200
1,300
Cash collections during the
year
1,000
1,500
Compute the amount of revenue and gross profit recognized
during 2017 and 2018.
Assume that McCombs recognizes revenue on this contract over...
Hardhat Contractors received a contract to construct a bridge
for $4,500,000. Construction was begun in 2014...
Hardhat Contractors received a contract to construct a bridge
for $4,500,000. Construction was begun in 2014 and completed in
2015. Cost and other data are presented below:
2014
2015
Costs incurred during the year
1,500,000
2,700,000
Estimated costs to complete
2,500,000
-
Billings during the year
1,900,000
2,500,000
Cash collections during that year
1,700,000
2,600,000
Assume that Hardhat Contractors uses the
percentage-of-completion method for revenue recognition. Compute
the amount of gross profit recognized during 2014 and 2015.
2014
2015
Contract...
Using Percentage-of-Completion and Completed Contract
Methods
Halsey Building Company signed a contract to build an office...
Using Percentage-of-Completion and Completed Contract
Methods
Halsey Building Company signed a contract to build an office
building for $60,000,000. The scheduled construction costs
follow.
Year
Cost
2016
$12,000,000
2017
18,000,000
2018
10,000,000
Total
$40,000,000
The building is completed in 2018.
For each year, compute the revenue, expense, and gross profit
reported for this construction project using each of the following
methods.
a. Percentage-of-completion method
2016
2017
2018
Revenue
$Answer
$Answer
$Answer
Expense
$Answer
$Answer
$Answer
Gross Profit
$Answer
$Answer
$Answer...
On June 15, 2018, Sanderson Construction entered into a
long-term construction contract to build a baseball...
On June 15, 2018, Sanderson Construction entered into a
long-term construction contract to build a baseball stadium in
Washington, D.C., for $330 million. The expected completion date is
April 1, 2020, just in time for the 2020 baseball season. Costs
incurred and estimated costs to complete at year-end for the life
of the contract are as follows ($ in millions):
2018
2019
2020
Costs incurred during the year
$
90
$
70
$
45
Estimated costs to complete as of...
During 2020, Carla Company started a construction job with a
contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a
contract price of $1,600,000. The job was completed in 2022. The
following information is available.
2020
2021
2022
Costs incurred to date
$405,900
$830,680
$1,074,000
Estimated costs to complete
584,100
262,320
–0–
Billings to date
302,000
898,000
1,600,000
Collections to date
272,000
818,000
1,420,000
Correct answer iconYour answer is correct.
Compute the amount of gross profit to be recognized each year,
assuming the percentage-of-completion method is used.
Gross profit recognized...