On January 4th, Stevens Manufacturing received an order for 30
uniforms. The following information pertained to that
order.
Hours Required
Receive and process order 0.25
Waiting for production to begin 1.25
Cutting 50.00
Sewing and lettering 300.00
Moving materials from one station to another 20.00
Waiting for an operation to begin 95.00
Packaging 35.00
Loading to be shipped 0.50
In transit to customer 5.00
Calculate the manufacturing cycle efficiency.
a.69%
b. 60%
c. 70%
d. 10%
Manufacturing cycle efficiency=(MCE)= Total value added time÷total manufacturing process time
Now , MCE is = 350 hours^ ÷507 hour^^= .69 that is 69 %
So answer a is currect
1.Value added time=
Cutting time 50 hours
Sewing time 300 hours
Total time 350 hours
2 Total process time
Value added time 350
Receive and process odder .25
Waiting for production 1.25
Moving material 20
Waiting for opratiope to begain 95
Packing 35
Loading .50
Transit to custmer 5.00
Total time - 507 hours