Question

The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...

The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows:

Standard Costs
Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.78 per hour
Variable overhead 3 hours per unit @ $1.91 per hour

Actual Costs
    Total variable cost, $17,800
    Total fixed cost, $8,100

The variable factory overhead controllable variance is

a.$1,756 favorable

b.$1,756 unfavorable

c.$1,405 favorable

d.$0

Homework Answers

Answer #1

Option B

1. variable factory overhead controllable variance

variable factory overhead controllable variance = Actual OH - Budgeted OH based on standard hours

variable factory overhead controllable variance = $17800 - Units Produced * Standard Hours * $ per hour

variable factory overhead controllable variance = $17800 - 2800 * 3 * $1.91

variable factory overhead controllable variance = $17800 - $16044

variable factory overhead controllable variance = $1756 Unfavourable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
1. Standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.77 per hour Variable overhead 3 hours per unit @ $1.91 per hour Actual Costs     Total variable cost, $18,100     Total fixed cost, $8,200 The amount of the variable factory overhead controllable variance is a.$2,056 favorable b.$0 c.$2,056 unfavorable d.$1,645 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.71 per hour Variable overhead 3 hours per unit at $2.06 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,000 The fixed factory overhead volume variance is a.$0 b.$909 unfavorable c.$1,136 unfavorable d.$909 favorable
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour Variable overhead 3 hours per unit @ $2.01 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $7,900 The total factory overhead cost variance is a.$-90 unfavorable b.$610 unfavorable c.$1,310 favorable d.$610 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,500 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.75 per hour Variable overhead 3 hours per unit @ $1.97 per hour Actual Costs     Total variable cost, $17,900     Total fixed cost, $8,000 The amount of the total factory overhead cost variance is a.$5,000 favorable b.$5,000 unfavorable c.$3,125 unfavorable d.$6,875 favorable
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.70 per hour Variable overhead 3 hours per unit @ $1.99 per hour Actual Costs     Total variable cost, $17,900     Total fixed cost, $8,200 The total factory overhead cost variance is a.$-10 unfavorable b.$690 unfavorable c.$1,390 favorable d.$690 favorable
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.72 per hour Variable overhead 3 hours per unit at $1.99 per hour Actual Costs Total variable cost, $17,800 Total fixed cost, $7,900 The total factory overhead cost variance is
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.72 per hour Variable overhead 3 hours per unit @ $2.06 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $7,900 The fixed factory overhead volume variance is a.$720 unfavorable b.$0 c.$576 unfavorable d.$576 favorable The following data are given for Bahia Company: Budgeted...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 994 units were actually produced. Labor standards were 7.6 hours per completed unit at a standard rate of $12.86 per hour. The direct labor rate variance is a.$6,881.72 unfavorable b.$6,881.72 favorable c.$5,577.18 unfavorable d.$5,577.18 favorable 21. Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.08 per hour. Original...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $223,100 Fixed factory overhead 94,250 Standard: 8,000 hrs. at $36 288,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $324,250, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $7.25 per hour....
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead...
Direct Materials, Direct Labor, and Reports budgeted and actual costs for variable and fixed factory overhead along with the related controllable and volume variances.Factory Overhead Cost Variance Analysis Mackinaw Inc. processes a base chemical into plastic. A detailed estimate of what a product should cost.Standard costs and actual costs for direct materials, direct labor, and factory overhead incurred for the manufacture of 6,800 units of product were as follows: Standard Costs Actual Costs Direct materials 8,800 lb. at $4.90 8,700...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT