Mickey Mouse Corporation’s plantwide overhead rate is $66 per hour. Factory workers (direct labor) are paid $48 per hour. Compute the total cost for completing Job No. 101. Job 101 was an order for 100 Widgets. Compute the cost per Widget.
a. Direct labor for Job 101…………….$1,800
b. Direct materials for Job 101………$5,420
Direct Labor Cost= $ 1,800
Direct Labor rate per hour = $ 48 per hour
Hence, direct labor hours = Direct Labor / Direct Labor rate per hour
= $ 1,800 / $ 48
= 37.50 hours
Overhead = Direct labor hours * plant wide overhead rate
= 37.50 Hours * $ 66
= $ 2,475
Total Cost = Direct labor + Direct materials+ Overhead
= $ 1,800 + $ 5,420 + $ 2,475
= $ 9,695
Cost per Widget = Total Cost / Total Widgets
= $ 9,695 / 100 Widgets
= $ 95.95
Hence the correct answer is $ 95.95