Question

Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...

Factory Overhead Cost Variances

The following data relate to factory overhead cost for the production of 3,000 computers:

Actual: Variable factory overhead $122,200
Fixed factory overhead 35,000
Standard: 3,000 hrs. at $49 147,000

If productive capacity of 100% was 5,000 hours and the total factory overhead cost budgeted at the level of 3,000 standard hours was $161,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $7 per hour. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Variance Amount Favorable/Unfavorable
Controllable variance $ Favorable
Volume variance $ 14000 Unfavorable
Total factory overhead cost variance $ Unfavorable

Homework Answers

Answer #1

1.Variable Factory overhead controllable variance.

Actual Variable Factory overhead incurred = $ 122200

Budgeted factory variable overhead for $3000hrs = $ 126000

(3000* (49-7))

Favourable variance = - $ 3800 (minus $3800)

2. Fixed factory overhead volume variance

Total production capacity at 100% = 5000hours

Standard production = 3000hours

Production capacity not used = 2000hours

Standard fixed factory overhead rate = $7 per hour

Unfavourable variance = $ 14000 (positive $ 14000)

Total Factory overhead cost variance - Unfavourable = $10200 (positive)

Conclusion:

Variance Amount Favorable/Unfavorable
Controllable variance $-3800 Favourable
Volume variance $ 14000 Unfavorable
Total factory overhead cost variance $10200 Unfavorable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $98,500 Fixed factory overhead 38,500 Standard: 7,000 hrs. at $18 126,000 If productive capacity of 100% was 11,000 hours and the factory overhead cost budgeted at the level of 7,000 standard hours was $140,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Actual: Variable factory overhead $65,000 Fixed factory overhead 25,500 Standard: 4,000 hrs. at $21 84,000 If productive capacity of 100% was 6,000 hours and the total factory overhead cost budgeted at the level of 4,000 standard hours was $92,500, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 7,000 computers: Actual: Variable factory overhead $297,100 Fixed factory overhead 68,750 Standard: 7,000 hrs. at $50 350,000 If productive capacity of 100% was 11,000 hours and the total factory overhead cost budgeted at the level of 7,000 standard hours was $375,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Actual: Variable factory overhead $90,200 Fixed factory overhead 34,500 Standard: 4,000 hrs. at $29 116,000 If productive capacity of 100% was 6,000 hours and the total factory overhead cost budgeted at the level of 4,000 standard hours was $127,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
Accounting thx! Factory Overhead Cost Variances The following data relate to factory overhead cost for the...
Accounting thx! Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 3,000 computers: Actual: Variable factory overhead $112,000 Fixed factory overhead 27,500 Standard: 3,000 hrs. at $44 132,000 If productive capacity of 100% was 5,000 hours and the total factory overhead cost budgeted at the level of 3,000 standard hours was $143,000, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $190,100 Fixed factory overhead 45,500 Standard: 8,000 hrs. at $28 224,000 If productive capacity of 100% was 13,000 hours and the factory overhead cost budgeted at the level of 8,000 standard hours was $241,500, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 4,000 computers: Actual: Variable factory overhead $116,400 Fixed factory overhead 30,000 Standard: 4,000 hrs. at $35 140,000 If productive capacity of 100% was 6,000 hours and the factory overhead cost budgeted at the level of 4,000 standard hours was $150,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
Factory Overhead Cost Variances The following data relate to factory overhead cost for the production of 5,000 computers: Actual: Variable factory overhead $104,300 Fixed factory overhead 28,000 Standard: 5,000 hrs. at $25 125,000 If productive capacity of 100% was 8,000 hours and the total factory overhead cost budgeted at the level of 5,000 standard hours was $135,500, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of...
actory Overhead Cost Variances The following data relate to factory overhead cost for the production of 5,000 computers: Actual: Variable factory overhead $97,000 Fixed factory overhead 32,000 Standard: 5,000 hrs. at $24 120,000 If productive capacity of 100% was 8,000 hours and the total factory overhead cost budgeted at the level of 5,000 standard hours was $132,000, determine the variable factory overhead Controllable Variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable...
The following data relate to factory overhead cost for the production of 8,000 computers: Actual: Variable factory overhead $223,100 Fixed factory overhead 94,250 Standard: 8,000 hrs. at $36 288,000 If productive capacity of 100% was 13,000 hours and the total factory overhead cost budgeted at the level of 8,000 standard hours was $324,250, determine the variable factory overhead controllable variance, fixed factory overhead volume variance, and total factory overhead cost variance. The fixed factory overhead rate was $7.25 per hour....
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT