Question 1 is Part A,B,c, and D
A.
Oliver Enterprises has collected the following data for one of its products:
Direct materials standard
(7 pounds per unit @$0.56/lb.) |
$3.92 per finished good |
Direct materials flexible budget
variance−unfavorable |
$12,000 |
Actual Direct Materials Used (AQU) |
35,000 pounds |
Actual finished goods produced |
21,000 units |
What is the total actual cost of the direct materials used?
A.$137,200
B.$82,320
C.$94,320
D.$70,320
B. The following information describes a company's usage of direct labor in a recent period:
Actual direct labor hours used |
$36,000 |
Actual rate per hour |
$24.00 |
Standard rate per hour |
$12.50 |
Standard hours for units produced |
33,500 |
How much is the direct labor rate variance?
A.$414,000 favorable
B. $385,250 unfavorable
C. $414,000 unfavorable
D. $385,250 favorable
C. The actual cost of direct labor per hour is $15.75. Two and one half standard direct labor hours are allowed per unit of finished goods. During the current period, 3,500 units were produced using 8,450 direct labor hours. The direct labor efficiency variance is $2,600 favorable. Calculate the standard direct labor rate per hour.
A. $0.74
B.$8.67
C. $15.75
D. $3.37
D.
Speaker City designs and manufactures high−end home theater speakers. Speaker City uses a standard variable overhead rate of 4.5 hours per unit at a cost of $12.00 per hour. Data for the month of June shows that Speaker City produce 600 units and recorded actual variable overhead costs of $46,000.
What is the total variable overhead variance for the month ofJune?
A. $13,600 unfavorable
B. $38,800 favorable
C. $13,600 favorable
D. $38,800 unfavorable
A.
Direct material flexible budget variance = Actual results - Flexible budget
-$12,000 = Actual results - $82,320 (21,000*$3.92)
Actual results = $82,320-12,000 = $70,320
The total actual cost of direct material used is $70,320
Hence option D is correct.
B.
Direct labor rate variance = Actual hours*Standard rate - Actual hours*Actual rate
Direct labor rate variance = 36,000*$12.50 - 36,000*$24
Direct labor rate variance = $450,000 - 864,000 = $414,000 Unfavorable
Hence option C is correct.
C.
Direct labor efficiency variance = (Standard hours - Actual hours) * Standard rate
$2,600 = (3,500*2.5 - 8,450) * Standard rate
$2,600 = 300 * Standard rate
Standard rate = $2,600 / 300 = $8.67 per hour
Hence option B is correct.
D.
Total variable overhead variance = Actual variable overhead cost - (Actual output * Standard rate per output)
Total variable overhead variance = $46,000 - (600*4.5*$12)
Total variable overhead variance = $46,000 - $32,400= $13,600 Unfavorable
Hence option A is correct.
Get Answers For Free
Most questions answered within 1 hours.