Question

Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order...

Taveras Corporation is currently operating at 50% of its available manufacturing capacity. It uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:

Machine-hours required to support estimated production 205,000
Fixed manufacturing overhead cost $ 3,075,000
Variable manufacturing overhead cost per machine-hour $ 2.00

Required:

1. Compute the plantwide predetermined overhead rate.

2. During the year, Job P90 was started, completed, and sold to the customer for $3,300. The following information was available with respect to this job:

Direct materials $ 1,518
Direct labor cost $ 1,089
Machine-hours used 80

Compute the total manufacturing cost assigned to Job P90.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Maria Company uses a job order costing system with a plantwide overhead rate on machine-hours. At...
Maria Company uses a job order costing system with a plantwide overhead rate on machine-hours. At the beginning of the year, the company made the following estimates: Machine Hours estimated to support estimated production      210,000 Fixed manufacturing overhead cost $3,360,000.00 Variable manufacturing overhead cost per machine-hour $              2.00 During the year, Job P90 was started, completed, and sold to the customer. The following information was available with respect to this job. Direct materials $1,564.00 Direct labor cost $1,122.00 Machine-hours used...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates Machine-hours required to support estimated production 200,000 Fixed manufacturing overhead cost $1,300,000 Variable manufacturing overhead cost per machine-hour $3.00 1.a - Compute the predetermined overhead rate – (12 points) 1. b - During the year, Job 400 was started and completed. The following information was available with respect to this job Direct materials...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 153,000 Fixed manufacturing overhead cost $ 654,000 Variable manufacturing overhead cost per machine-hour $ 4.70 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 151,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.90 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 152,000 Fixed manufacturing overhead cost $ 654,000 Variable manufacturing overhead cost per machine-hour $ 5.00 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours....
Moody Corporation uses a job-order costing system with a plantwide predetermined overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates: Machine-hours required to support estimated production 155,000 Fixed manufacturing overhead cost $ 658,000 Variable manufacturing overhead cost per machine-hour $ 4.40 Required: 1. Compute the plantwide predetermined overhead rate. 2. During the year, Job 400 was started and completed. The following information was available with respect to this job: Direct materials $...
6.       Moody Corporation uses a job- order costing system with a plantwide overhead rate based on...
6.       Moody Corporation uses a job- order costing system with a plantwide overhead rate based on machine- hours. At the beginning of the year, the company made the following estimates: Machine- hours required to support estimated production . . . . . . 100,000 Fixed manufacturing overhead cost . . . . . . . . . . . . . . . . . . . . . . . . $ 650,000 Variable manufacturing overhead cost per machine-...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At...
Moody Corporation uses a job-order costing system with a plantwide overhead rate based on machine-hours. At the beginning of the year, the company made the following estimates:     Machine-hours required to support estimated production . . . . . . 100,000     Fixed manufacturing overhead cost . . . . . . . . . . . . . . . . . . . . . . . . $650,000    Variable manufacturing overhead cost per machine-hour . ....
Landen Corporation uses a job-order costing system. At the beginning of the year, the company made...
Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 130,000 Machine-hours required to support estimated production 65,000 Fixed manufacturing overhead cost $ 364,000 Variable manufacturing overhead cost per direct labor-hour $ 4.00 Variable manufacturing overhead cost per machine-hour $ 8.00 During the year, Job 550 was started and completed. The following information is available with respect to this job: Direct materials $ 253...
Landen Corporation uses a job-order costing system. At the beginning of the year, the company made...
Landen Corporation uses a job-order costing system. At the beginning of the year, the company made the following estimates: Direct labor-hours required to support estimated production 135,000 Machine-hours required to support estimated production 67,500 Fixed manufacturing overhead cost $ 378,000 Variable manufacturing overhead cost per direct labor-hour $ 4.20 Variable manufacturing overhead cost per machine-hour $ 8.40 During the year, Job 550 was started and completed. The following information is available with respect to this job: Direct materials $ 196...