Question

Comparison of Regression Equations Friendly Bank is attempting to determine the cost behavior of its small...

Comparison of Regression Equations

Friendly Bank is attempting to determine the cost behavior of its small business lending operations. One of the major activities is the application activity. Two possible activity drivers have been mentioned: application hours (number of hours to complete the application) and number of applications. The bank controller has accumulated the following data for the setup activity:

Month Application Costs Application Hours Number of Applications
February $7,700     2,000         70            
March 7,650     2,100         50            
April 10,052     3,000         50            
May 9,400     2,700         60            
June 9,584     3,000         20            
July 8,480     2,500         40            
August 8,550     2,400         60            
September 9,735     2,900         50            
October 10,500     3,000         90            

Required:

In the computations below, use intercepts rounded to the nearest whole number and use X variable coefficients rounded to 2 decimal places.

1. Estimate a regression equation with application hours as the activity driver and the only independent variable. If the bank forecasts 2,600 application hours for the next month, what will be the budgeted application cost? Round your answer to the nearest dollar.

$_____________________

2. Estimate a regression equation with number of applications as the activity driver and the only independent variable. If the bank forecasts 80 applications for the next month, what will be the budgeted application cost? Round your answer to the nearest dollar.

$_____________________

3. Which of the two regression equations do you think does a better job of predicting application costs? Choose the correct answer: 1. Applications hours or 2. Number of applications.

4. Run a multiple regression to determine the cost equation using both activity drivers. What are the budgeted application costs for 2,600 application hours and 80 applications? Round your answer to the nearest cent.

$_______________

Homework Answers

Answer #1
X Application hours
Y Application Cost
x y XY x*x Y*Y
February 2000 7700 15400000 4000000 59290000
March 2100 7650 16065000 4410000 58522500
April 3000 10052 30156000 9000000 101042704
May 2700 9400 25380000 7290000 88360000
June 3000 9584 28752000 9000000 91853056
July 2500 8480 21200000 6250000 71910400
August 2400 8550 20520000 5760000 73102500
September 2900 9735 28231500 8410000 94770225
October 3000 10500 31500000 9000000 110250000
Total 23600 81651 217204500 63120000 749101385
a = (?y)(?x*x)-(?x)(?xy)/n(?x*x)-(?x)*(?x)
b = n(?xy)-(?x)(?y)/n(?x*x)-(?x)*(?x)

a =

27784920000/11120000 =
2498.643885

b = 2.5

Regression Equation = y = 2498.64+2.5x

If x = 2600 hours then Application Cost(y) = 2498.64+2.5(2600)=$8999

2)

X = Number of Applications

Y = Application Cost

x y XY x*x Y*Y
February 70 7700 539000 4900 59290000
March 50 7650 382500 2500 58522500
April 50 10052 502600 2500 101042704
May 60 9400 564000 3600 88360000
June 20 9584 191680 400 91853056
July 40 8480 339200 1600 71910400
August 60 8550 513000 3600 73102500
September 50 9735 486750 2500 94770225
October 90 10500 945000 8100 110250000
Total 490 81651 4463730 29700 749101385
a = (?y)(?x*x)-(?x)(?xy)/n(?x*x)-(?x)*(?x)

b = n(?xy)-(?x)(?y)/n(?x*x)-(?x)*(?x)

a =

237807000/27200 = 8742.90

b = 6.05

Regression Equation = y = 8742.90+6.05x

If x = 80 Applications then Application Cost(y) = 8742.90+6.05(80)=$9227

3) Application hours shall be taken as better job of predicting Application cost since Cost is incurred in proportionate to time consumed for the respective number of applications

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine...
Using Regression to Calculate Fixed Cost, Calculate the Variable Rate, Construct a Cost Formula, and Determine Budgeted Cost Speedy Pete’s is a small start-up company that delivers high-end coffee drinks to large metropolitan office buildings via a cutting-edge motorized coffee cart to compete with other premium coffee shops. Data for the past 8 months were collected as follows: Month Delivery Cost Number of Deliveries May $63,450 1,800 June 67,120 2,010 July 66,990 2,175 August 68,020 2,200 September 73,400 2,550 October...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to...
Zayner Company is a job-order costing firm that use activity based costing to apply overhead to jobs. Zayner identified three overhead activities and their related drivers. Budgeted information for the year is as follows: Zayner Company is a job order costing company that uses activity-based costing (ABC) to apply manufacturing overhead to different jobs. Zayner identified three activities and the related cost drivers. The budgeted information (budget) for the year is as follows: Activity Cost Driver Amount of Driver Engineering...
Time Remaining 22 minutes 50 seconds 00:22:50 ItemSkipped Item 4 Item 4 Item Skipped Time Remaining...
Time Remaining 22 minutes 50 seconds 00:22:50 ItemSkipped Item 4 Item 4 Item Skipped Time Remaining 22 minutes 50 seconds 00:22:50 Sheen Co. manufacturers laser printers. It has outlined the following overhead cost drivers: Overhead Costs Pool Cost Driver Overhead Cost Budgeted Level for Cost Driver Quality control Number of inspections $ 75,000 1,500 Machine operation Machine hours 146,000 1,000 Materials handling Number of batches 900 30 Miscellaneous overhead cost Direct labor hours 54,000 4,500 Sheen Co. has an order...
A company has identified the following overhead costs and cost drivers for the coming year:     ...
A company has identified the following overhead costs and cost drivers for the coming year:               Budgeted   Overhead Item   Cost Driver Budgeted Cost    Activity Level   Machine setup   Number of setups $ 25,300           220           Inspection   Number of inspections 124,200         4,600           Material handling   Number of material moves 99,200         6,200           Engineering   Engineering hours 12,400         620                  Budgeted direct labor cost was $130,550 and budgeted direct material cost was $369,540. The following information was collected on...
PLEASE ANSWER ALL QUESTIONS AND SHOW YOUR WORK! Job 101 has a direct materials cost of...
PLEASE ANSWER ALL QUESTIONS AND SHOW YOUR WORK! Job 101 has a direct materials cost of $800 and a total manufacturing cost of $3,000. Overhead is applied to jobs at a rate of 150 percent of direct labor cost. What is the prime cost? ------------------------- Walnut Systems produces two different products, Product A, which sells for $124 per unit, and Product B, which sells for $196 per unit, using three different activities: Design, which uses Engineering Hours as an activity...
4.) X Company uses an activity-based costing allocation system. On January 1, 2020, its accountant budgeted...
4.) X Company uses an activity-based costing allocation system. On January 1, 2020, its accountant budgeted the following costs and cost drivers for three of the activities that are used in the ABC system: Activity   Budgeted cost   Cost driver Assembly   $134,000   92,700 parts Packaging   $80,400   13,000 finished units Purchasing   $53,600   4,700 purchase orders In May of 2020, 563 units of Product C were finished, requiring $10,100 of direct materials, 5,000 direct labor hours, 1,410 parts, and 34 purchase orders. How...
Elevated Expectations Company projected the following overhead costs and cost drivers for past year (assume that...
Elevated Expectations Company projected the following overhead costs and cost drivers for past year (assume that actual overhead and budgeted overhead were the same): Overhead Item Expected Costs Cost Driver Expected Quantity Setup costs $12,150 Number of setups 50 Ordering costs 4,050 Number of orders 30 Maintenance 17,400 Machine-hours 600 Power 3,000 Kilowatt-hours 600 Direct Labor Hours 500 Elevated Expectations contracted for 2 jobs, both of which were completed during the year. Production managers reported the following data in relation...
Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its...
Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $636,400, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Assembly setups 132,000 Materials handling 64,800 Assembly 360,000 Maintenance 79,600 Total: 206,700 Cost Drivers Activity Level Setup hours 2,000 Number of moves 600 Assembly hours 18,000 Maintenance hours 1,990 Total direct labor hours used during the month were 14,800. Panasonic produces many different electronic products,...
Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its...
Assume that Panasonic Company has determined its estimated total manufacturing overhead cost for one of its plants to be $1,591,000, consisting of the following activity cost pools for the current month: Activity Centers Activity Costs Cost Drivers Activity Level Assembly setups $ 330,000 Setup hours 2,000 Materials handing 162,000 Number of moves 600 Assembly 900,000 Assembly hours 18,000 Maintenance 199,000 Maintenance hours 1,990 Total $1,591,000 Total direct labor hours used during the month were 14,800. Panasonic produces many different electronic...
An important application of regression analysis in accounting is in the estimation of cost. By collecting...
An important application of regression analysis in accounting is in the estimation of cost. By collecting data on volume and cost and using the least squares method to develop an estimated regression equation relating volume and cost, an accountant can estimate the cost associated with a particular manufacturing volume. Consider the following sample of production volumes and total cost data for a manufacturing operation. Production Volume (units) Total Cost ($) 400 4,000 450 5,000 550 5,400 600 5,900 700 6,400...