The Lakeside Company uses a weighted-average process costing system. The following data are available:
Beginning inventory | -0- | ||
Units started in production | 22,600 | ||
Units finished during the period | 17,200 | ||
Units in process at the end of the period (complete as to materials, ¼ complete as to labor and overhead) | 5,400 |
||
Cost of materials used | $ | 51,120 | |
Labor and overhead costs | $ | 39,165 | |
Total cost of the 17,200 units finished is: (Round intermediate calculations to two decimal places and round your final answer to the nearest whole dollar).
$93,079.