Question

Department S had no work in process at the beginning of the period. It added 11,800...

Department S had no work in process at the beginning of the period. It added 11,800 units of direct materials during the period at a cost of $94,400. During the period, 8,900 units were completed, and 2,900 units were 30% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. Direct labor was $72,298, and factory overhead was $31,264.

The total cost of units completed during the period was

a.$71,200

b.$165,540

c.$137,060

d.$198,648

Homework Answers

Answer #1
Beginning work in process 0 completed & transferred 8,900
started during the year 11,800 ending work in prcess 2,900
units to be accounted 11800 units accounted for 11,800
Equilvalent units
% mater Materials % CC CC
completed & transferred 8,900 100% 8,900 100% 8,900
Ending work in process 2,900 100% 2,900 30% 870
11,800 9,770
cost per unit
materials CC total
beginning work in process 0 0 0
cost added during the yer 94,400 103562 197,962
total cost 94400 103562 197962
equivalent units 11,800 9770
cost per unit 8 10.6 18.6
hence total cost of units transferred = 8900*18.6
165540
option b) answer
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Department S had no work in process at the beginning of the period. It added 13,800...
Department S had no work in process at the beginning of the period. It added 13,800 units of direct materials during the period at a cost of $96,600; 10,350 units were completed during the period; and 3,450 units were 30% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. Direct labor was $53,300 and factory overhead was $9,600. The total cost of units completed during the period...
Department S had no work in process at the beginning of the period. It added 13,600...
Department S had no work in process at the beginning of the period. It added 13,600 units of direct materials during the period at a cost of $108,800. During the period, 10,200 units were completed, and 3,400 units were 30% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. Direct labor was $83,028, and factory overhead was $17,952. The total cost of units completed during the period...
Department S had no work in process at the beginning of the period. It added 13,800...
Department S had no work in process at the beginning of the period. It added 13,800 units of direct materials during the period at a cost of $96,600. During the period, 10,400 units were completed, and 3,400 units were 35% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. Direct labor was $64,904, and factory overhead was $34,770. The total cost of units completed during the period...
Department S had no work in process at the beginning of the period. It added 11,200...
Department S had no work in process at the beginning of the period. It added 11,200 units of direct materials during the period at a cost of $78,400; 8,400 units were completed during the period; and 2,800 units were 36% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. Direct labor was $50,900 and factory overhead was $8,000. The total cost of units completed during the period...
Department A had no Work-in-Process at the beginning of the period, 1,900 units were completed during...
Department A had no Work-in-Process at the beginning of the period, 1,900 units were completed during the period, 650 units were 50% completed at the end of the period, and the following manufacturing costs were debited to the departmental Work-in-Process account during the period   Direct materials (2,550 at $19.00) $ 48,450     Direct labor 24,030     Factory overhead 16,020   Assuming that all direct materials are added at the beginning of production and Department A uses weighted-average process costing, what is the total...
department G had 8000 units in work in process that were 40% converted at the beginning...
department G had 8000 units in work in process that were 40% converted at the beginning of the period at a cost of 19450. During the period, 18000 units of direct materials were added at a cost of $54000, 18500 units were completed, and 7500 units were 40% completed. The first in, first out method is used and all the materials are added at the beginning of the4 process. Direct labor was $32,500, and factory overhead was $66320 during the...
1) Department F had 4,000 units in Work in Process that were 40% completed at the...
1) Department F had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $14,400. Of the $14,400, $8,900 was for material and $5,500 was for conversion costs. 14,000 units of direct materials were added during the period at a cost of $31,800. 15,000 units were completed during the period, and 3,000 units were 75% completed at the end of the period. All materials are added at the beginning of...
Department E had 4,000 units in Work in Process that were 40% completed at the beginning...
Department E had 4,000 units in Work in Process that were 40% completed at the beginning of the period at a cost of $12,500. During the period, 14,000 units of direct materials were added at a cost of $28,700 and 15,000 units were completed. At the end of the period, 3,000 units were 75% completed. All materials are added at the beginning of the process. Direct labor was $32,450, and factory overhead was $18,710. The number of equivalent units of...
department G had 8000 units in work in process that were 40% converted at the beginning...
department G had 8000 units in work in process that were 40% converted at the beginning of the period at a cost of 19450. During the period, 18000 units of direct materials were added at a cost of $54000, 18500 units were completed, and 7500 units were 40% completed. The first in, first out method is used and all the materials are added at the beginning of the4 process. Direct labor was $32,500, and factory overhead was $66320 during the...
Department R had 4,400 units in work in process that were 80% completed as to labor...
Department R had 4,400 units in work in process that were 80% completed as to labor and overhead at the beginning of the period; 38,000 units of direct materials were added during the period; 40,300 units were completed during the period; and 2,100 units were 30% completed as to labor and overhead at the end of the period. All materials are added at the beginning of the process. The first-in, first-out method is used to cost inventories. The number of...