Question

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows:

2018

2019

2020

Cost incurred during the year

$

2,580,000

$

4,042,000

$

2,175,800

Estimated costs to complete as of year-end

6,020,000

1,978,000

0

Billings during the year

2,060,000

4,562,000

3,378,000

Cash collections during the year

1,830,000

4,200,000

3,970,000


Westgate recognizes revenue over time according to percentage of completion.
Required:
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information.

2018

2019

2020

Cost incurred during the year

$

2,580,000

$

3,830,000

$

3,990,000

Estimated costs to complete as of year-end

6,020,000

4,160,000

0

Req 5

Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs incurred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.)

2018

2019

2020

Revenue

$3,000,000

$3,064,333

$3,935,667

Gross profit (loss)

$420,000

Please calculate Gross profit (loss) in 2019 and 2020.

Homework Answers

Answer #1

Solution:

Computation of % of completion, revenue recognition and Gross Profit - Westgate Construction Company
Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of completion (D) (B/C) Contract Price
(E)
Total Revenue to be recoganized (F) (E * D) Revenue for current period (G) Gross Profit
2018 $2,580,000.00 $2,580,000.00 $8,600,000.00 30% $10,000,000.00 $3,000,000.00 $3,000,000 $420,000.00 $3,000,000 - $2,580,000
2019 $3,830,000.00 $6,410,000.00 $10,570,000.00 61% $10,000,000.00 $6,064,333.02 $3,064,333 -$990,000.00 $10,000,000 - $10,570,000 - $420,000
2020 $3,990,000.00 $10,400,000.00 $10,400,000.00 100% $10,000,000.00 $10,000,000.00 $3,935,667 $170,000.00 $10,570,000 - $10,400,000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year 1,830,000 4,200,000 3,970,000 Westgate recognizes revenue over time according to...
[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company...
[The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during the year...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate...
Required information [The following information applies to the questions displayed below.]    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,580,000 $ 4,042,000 $ 2,175,800 Estimated costs to complete as of year-end 6,020,000 1,978,000 0 Billings during the year 2,060,000 4,562,000 3,378,000 Cash collections during...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,072,000 $ 2,738,000 $ 2,849,000 Estimated costs to complete as of year-end 5,328,000 2,590,000 0 Billings during the year 2,160,000 2,650,000 5,190,000 Cash collections during the year 1,880,000 2,700,000 5,420,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,400,000 $ 3,600,000 $ 2,200,000 Estimated costs to complete as of year-end 5,600,000 2,000,000 0 Billings during the year 2,000,000 4,000,000 4,000,000 Cash collections during the year 1,800,000 3,600,000 4,600,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...