Air United, Inc. manufactures two products: missile range
instruments and space pressure gauges. During April, 50
range instruments and 200 pressure gauges were produced, and
overhead costs of $ 85,150 were estimated. An analysis of estimated
overhead costs reveals the following activities.
Activities |
Cost Drivers |
Total Cost |
||||
---|---|---|---|---|---|---|
1. | Materials handling | Number of requisitions |
$ 33,495 |
|||
2. | Machine setups | Number of setups |
27,645 |
|||
3. | Quality inspections | Number of inspections |
24,010 |
|||
$ 85,150 |
The cost driver volume for each product was as follows.
Cost Drivers |
Instruments |
Gauges |
Total |
|||
---|---|---|---|---|---|---|
Number of requisitions | 385 | 630 | 1,015 | |||
Number of setups | 185 | 300 | 485 | |||
Number of inspections | 260 | 230 | 490 |
Determine the overhead rate for each activity.
Overhead Rate |
|||
---|---|---|---|
Materials handling |
$ enter a dollar amount per requisition |
per requisition | |
Machine setups |
$ enter a dollar amount per setup |
per setup | |
Quality inspections |
$ enter a dollar amount per inspection |
per inspection |
eTextbook and Media
Assign the manufacturing overhead costs for April to the two products using activity-based costing. (Round per unit answers to 2 decimal places, e.g. 12.25.)
Instruments |
Gauges |
|||
---|---|---|---|---|
Total cost assigned |
$ enter a dollar amount rounded to 2 decimal places |
$ enter a dollar amount rounded to 2 decimal places |
||
Overhead cost per Unit |
$ enter a dollar amount rounded to 2 decimal places |
$ enter a dollar amount rounded to 2 decimal places |
Please hit LIKE button if this helped. For any further explanation, please put your query in comment, will get back to you. | |||||||
Overhead rate for each activity | |||||||
Activities | Cost Drivers | Total Cost | Total Cost Drivers | Overhead Rate | |||
1 | Materials handling | Number of requisitions | $ 33,495 | 1,015 | $ 33.00 | per requisition | |
2 | Machine setups | Number of setups | $ 27,645 | 485 | $ 57.00 | per setup | |
3 | Quality inspections | Number of inspections | $ 24,010 | 490 | $ 49.00 | per inspection | |
Total | $ 85,150 | ||||||
Instruments | Guage | ||||||
Activities | Overhead Rate | Cost Drivers | Cost | Cost Drivers | Cost | ||
Materials handling | $ 33 | 385 | $ 12,705 | 630 | $ 20,790 | ||
Machine setups | $ 57 | 185 | $ 10,545 | 300 | $ 17,100 | ||
Quality inspections | $ 49 | 260 | $ 12,740 | 230 | $ 11,270 | ||
Total Manufacturing overhead Cost assigned | $ 35,990 | $ 49,160 | |||||
No of Units | 50.00 | 200.00 | |||||
Cost per unit | $ 719.80 | $ 245.80 |