Question

Using the information for Headley Company from the previous problem, now assume there are no market...

Using the information for Headley Company from the previous problem, now assume there are no market constraints for either product, leaving the 250,000 labor hours as the only constraint and that Headley will make optimal use of its labor.  In early November, Headley was invited to bid on a contract to provide 2,000 units of Product B. What is the minimum bid Headley would have to submit in order to breakeven on the contract?

Product A                    Product B

Per Unit Information:

Selling Price/unit                                  $1,000                         $ 500

Direct Material Cost/unit $ 300                          $ 200

Direct Labor Cost (hours)/unit $ 200 (20 hrs) $ 100 (10 hrs)

Variable MO/unit ($4.00/hr) $   80 $ 40

Delivery Cost/unit $ 100                          $ 25

Fixed MO/unit ($2.00/hr)                      $   40 $ 20

Fixed Sell & Admin $   10 $ 5     

Budgeted Sales Units                            5,000 units                   15,000 units

Other Information:

  • The maximum number of direct labor hours available in a year are 250,000.
  • The market for product A is limited to 5,000 units per year, and the market for Product B is limited to 15,000 units per year- these market constraints are considered in the above budgeted sales units for the coming year.
  • The variable and fixed manufacturing overhead rates shown above $4.00/hr and $2.00/hr, respectively, are based upon using direct labor hours as the cost driver.
  • Fixed MO occurs evenly throughout the year and is considered unavoidable in the short term.
  • Fixed Selling and Administrative costs shown above are considered unavoidable in the short run and were arbitrarily allocated to Products A and B based on their respective budgeted sales revenues.
  • Delivery costs are always incurred for these products regardless of the customer purchasing them.

Use the information above to answer the next two questions.

Toward the end of the year it appears that the sales budget will be met. Thus, it appears the sales volume is going to be 5,000 units of Product A and 15,000 units of Product B. In early November, Headley was invited to bid on a contract to provide 2,000 units of Product B. What is the minimum bid Headley would have to submit in order to breakeven on the contract?

Group of answer choices

$1,000,000

$1,640,000

$1,050,000

$1,320,000

Homework Answers

Answer #1

Total hours required for existing units:

Product A 5000*20 hours 100,000
Product B 15000*10 150,000
Total hours 250,000

Maximum available hours => 250,000

Hence we do not have extra Labor capacity. Thus we should sell the existing units of product B.

So we need to reover the variable costs as well as the fixed costs and then the profit margin. This will make the selling price. Thus the minimum bid shall be for 2000*500 =$ 100,000

Hence Option A is correct  

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Based on a predicted level of production and sales of 15,000 units, a company anticipates total...
Based on a predicted level of production and sales of 15,000 units, a company anticipates total variable costs of $48,000, fixed costs of $21,000, and operating income of $81,600. Based on this information, the budgeted amount of operating income for 12,000 units would be: Multiple Choice $61,080. $82,080. $13,080. $38,400. $120,480. Fletcher Company collected the following data regarding production of one of its products. Compute the variable overhead spending variance. Direct labor standard (3.00 hrs. @ $18.20/hr.) $ 54.60 per...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.80 per Ib.) $ 144.00 Direct labor (7 hrs. @ $14 per hr.) 98.00 Factory overhead—variable (7 hrs. @ $6 per hr.) 42.00 Factory overhead—fixed (7 hrs. @ $9 per hr.) 63.00 Total standard cost $ 347.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 67,000 units per quarter. The following flexible budget...
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs....
Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4 per Ib.) $ 120.00 Direct labor (5 hrs. @ $14 per hr.) 70.00 Factory overhead—variable (5 hrs. @ $8 per hr.) 40.00 Factory overhead—fixed (5 hrs. @ $10 per hr.) 50.00 Total standard cost $ 280.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity of 60,000 units per quarter. The following flexible budget...
Sedona Company set the following standard costs for one unit of its product for this year....
Sedona Company set the following standard costs for one unit of its product for this year. Direct material (15 Ibs. @ $4.20 per Ib.) $ 63.00 Direct labor (10 hrs. @ $6.40 per hr.) 64.00 Variable overhead (10 hrs. @ $3.70 per hr.) 37.00 Fixed overhead (10 hrs. @ $1.50 per hr.) 15.00 Total standard cost $ 179.00 The $5.20 ($3.70 + $1.50) total overhead rate per direct labor hour is based on an expected operating level equal to 65%...
8. [The following information applies to the questions displayed below.] Sedona Company set the following standard...
8. [The following information applies to the questions displayed below.] Sedona Company set the following standard costs for one unit of its product for this year. Direct material (20 Ibs. @ $3.20 per Ib.) $ 64.00 Direct labor (10 hrs. @ $8.30 per hr.) 83.00 Variable overhead (10 hrs. @ $4.70 per hr.) 47.00 Fixed overhead (10 hrs. @ $2.30 per hr.) 23.00 Total standard cost $ 217.00 The $7.00 ($4.70 + $2.30) total overhead rate per direct labor hour...
6 .Isle company produces two products. Information on the 2 products is as follows – A...
6 .Isle company produces two products. Information on the 2 products is as follows – A B Selling price per unit $10 $4 Variable cost per unit $7 $2 Labour hours per unit 1 hr. 2 hrs. Market limitation 50,000 units 20,000 units Total labour hours available 75,000 hrs Total fixed cost $100,000 7. Using the information from question 6, assume there was no market limitation. What would be the best decision? a. Produce 50,000 units of A and 12,500...
The following information is available for DEF Company pertaining to its budgeted and actual activities for...
The following information is available for DEF Company pertaining to its budgeted and actual activities for the period. Item Budgeted Activity (10,000 units) Actual Activity (12,000 units) Sale Price $10.00 per unit $9.75 per unit Variable Costs (per unit) Direct Materials $2.00 per unit $1.89 per unit Direct Labor $3.00 per unit $3.05 per unit Factory Supplies $0.25 per unit $0.25 per unit Utilities $0.35 per unit $0.33 per unit Selling Costs $0.50 per unit $0.45 per unit Fixed Costs...
[The following information applies to the questions displayed below.] Antuan Company set the following standard costs...
[The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $4.00 per Ib.) $ 16.00 Direct labor (1.7 hrs. @ $13.00 per hr.) 22.10 Overhead (1.7 hrs. @ $18.50 per hr.) 31.45 Total standard cost $ 69.55 The predetermined overhead rate ($18.50 per direct labor hour) is based on an expected volume of 75% of the factory’s capacity of 20,000 units per month....
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead...
Required information Problem 21-3A Flexible budget preparation; computation of materials, labor, and overhead variances; and overhead variance report LO P1, P2, P3, P4 Skip to question [The following information applies to the questions displayed below.] Antuan Company set the following standard costs for one unit of its product. Direct materials (4.0 Ibs. @ $5.00 per Ib.) $ 20.00 Direct labor (1.6 hrs. @ $11.00 per hr.) 17.60 Overhead (1.6 hrs. @ $18.50 per hr.) 29.60 Total standard cost $ 67.20...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $2.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $384,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $4.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.20 per hour. The company planned to operate at a...