Mannassass Company manufactures chairs. The following information was given for the company:
units, beginning work in process 0
units started 20,000
units completed?
units, ending work in process 4,000
cost of direct materials $220,000
cost of conversion $ 27,520
Materials in the ending inventory were 100 percent complete and conversion in the ending inventory was 30 percent complete.
1. Refer to Figure 6-6. What are the units started and completed?
a. 20,000
b. 24,000
c. 16,000
d. 40,000
e. none of the above
2. Refer to Figure 6-6. What are the equivalent units for materials and conversion respectively?
a. 20,000; 20,000
b. 20,000; 16,000
c. 20,000; 17,200
d. 16,000; 14,000
e. none of the above
3. Refer to Figure 6-6. What are the costs per unit for materials and conversion respectively?
a. $22; $4
b. $28.33; $5.27
c. $11; $1.60
d. $84; $68
e. none of the above
4. Refer to Figure 6-6. What cost is assigned to ending work in process?
a. $45,920
b. $26,000
c. $100,000
d. $114,000
e. none of the above
Figure 6-12
Twinnings Corporation manufactures Scheduling Books. There are two processes: printing and binding. The following information is given for the printing department for September. (The company uses FIFO inventory assumption.)
Units:
units, beginning work in process 40,000 (30% complete for materials, 70% complete for conversion)
started 300,000
completed ?
units, ending work in process 50,000 (35% complete for materials, 90% complete for conversion)
Costs: Materials Conversion Total
beginning work in process $ 6,080 $ 2,160 $ 8,240
current costs $192,075 $33,770 $225,845
total costs $198,155 $35,930 $234,085
5. Refer to Figure 6-12. What are the FIFO equivalent units for materials?
a. 304,500
b. 294,500
c. 306,500
d. 295,500
e. none of the above
6. Refer to Figure 6-12. What are the FIFO equivalent units for conversion?
a. 306,000
b. 340,000
c. 317,000
d. 307,000
e. none of the above
(1) Units started and completed= Units started - Ending WIP
= 20000-4000= 16000
Option C is correct
(2)
Material | Conversion | |
Units completed & started | 16000 | 16000 |
Ending WIP |
(4000*100%) =4000 |
(4000*30%) =1200 |
Equivalent units | 20000 | 17200 |
Option C is correct
(3) Cost pu for material = 220000/20000 = 11
Cost pu for Conversion cost = 27520/17200. = 1.6
Option C is correct
(4) Cost assign to ending WIP
Material = 4000 * 11 = 44000
Conversion cost = 1200*1.6=1920
Total = 44000+1920=45920
Option A is correct
(5) &(6)
Material | Converion | |
Beginning WIP |
(40000*70%) 28000 |
(40000*30%) 12000 |
Units start & complete 300000-50000 | 250000 | 250000 |
Ending Wip |
(50000*35%) 17500 |
(50000*90%) 45000 |
Equivalent units | 295500 | 307000 |
Option D is correct for (5)
Option D is correct for (6)
Get Answers For Free
Most questions answered within 1 hours.