Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...

Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows:

Activity

Activity Rate

Fabrication $33 per machine hour
Assembly $18 per direct labor hour
Setup $56 per setup
Inspecting $20 per inspection
Production scheduling $12 per production order
Purchasing $8 per purchase order

The activity-base usage quantities and units produced for each product were as follows:

Elliptical

Activity Base

Machines

Treadmills

Machine hours 915 431
Direct labor hours 180 106
Setups 29 10
Inspections 163 183
Production orders 19 9
Purchase orders 94 50
Units produced 353 163

Required:

Use the activity rate and usage information to calculate the total activity cost and activity cost per unit for each product. Complete the Activity Tables for elliptical machines and treadmills. If required, round per-unit answers to the nearest cent.

Use the activity rate and usage information to calculate the total activity cost and activity cost per unit for elliptical machines product. Complete the Activity Table for elliptical machines. If required, round per-unit answers to the nearest cent.

Elliptical Machines
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Fabrication
Assembly
Setup
Inspecting
Production scheduling
Purchasing
Total activity cost
÷ Number of units ÷
Activity cost per unit

Use the activity rate and usage information to calculate the total activity cost and activity cost per unit for treadmill product. Complete the Activity Table for treadmills. If required, round per-unit answers to the nearest cent.

Treadmills
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Fabrication
Assembly
Setup
Inspecting
Production scheduling
Purchasing
Total activity cost
÷ Number of units ÷
Activity cost per unit

Homework Answers

Answer #1
Elliptical Machines
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Fabrication 915 33 30,195
Assembly 180 18 3,240
Setup 29 56 1,624
Inspecting 163 20 3,260
Production scheduling 19 12 228
Purchasing 94 8 752
Total activity cost 39,299
÷ Number of units ÷ 353
Activity cost per unit 111.33
Treadmills
Activity Activity-
Base Activity Activity
Usage X Rate = Cost
Fabrication 431 33 14,223
Assembly 106 18 1,908
Setup 10 56 560
Inspecting 183 20 3,660
Production scheduling 9 12 108
Purchasing 50 8 400
Total activity cost 20,859
÷ Number of units ÷ 163
Activity cost per unit 127.97
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $28 per machine hour Assembly $20 per direct labor hour Setup $75 per setup Inspecting $30 per inspection Production scheduling $12 per production order Purchasing $8 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $30 per machine hour Assembly $15 per direct labor hour Setup $54 per setup Inspecting $32 per inspection Production scheduling $16 per production order Purchasing $13 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $31 per machine hour Assembly $17 per direct labor hour Setup $46 per setup Inspecting $32 per inspection Production scheduling $18 per production order Purchasing $15 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $27 per machine hour Assembly $13 per direct labor hour Setup $49 per setup Inspecting $26 per inspection Production scheduling $14 per production order Purchasing $11 per purchase order The activity-base...
Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products...
Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $30 per machine hour Assembly $9 per direct labor hour Setup $56 per setup Inspecting $26 per inspection Production scheduling $10 per production order Purchasing $7...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $24 per machine hour Assembly $17 per direct labor hour Setup $51 per setup Inspecting $23 per inspection Production scheduling $18 per production order Purchasing $15 per...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $26 per machine hour Assembly $12 per direct labor hour Setup $55 per setup Inspecting $30 per inspection Production scheduling $13 per production order Purchasing $10 per...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $25 per machine hour Assembly $32 per direct labor hour Setup $87 per setup Inspecting $15 per inspection Production scheduling $14 per production order Purchasing $5 per...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product costs using activity rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $35 per machine hour Assembly $33 per direct labor hour Setup $94 per setup Inspecting $19 per inspection Production scheduling $18 per production order Purchasing $9 per...
Activity-Based Costing HealthTec Equipment Company manufactures stationary bicycles and treadmills. The products are produced in the...
Activity-Based Costing HealthTec Equipment Company manufactures stationary bicycles and treadmills. The products are produced in the Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $33 per machine hour (mh) Assembly $12 per direct labor hour (dlh) Setup $50 per setup Inspecting $30 per inspection Production scheduling $14 per production order Purchasing $8 per purchase...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT