Question

Setting Standards, Calculating and Using Variances Leather Works is a family-owned maker of leather travel bags...

Setting Standards, Calculating and Using Variances

Leather Works is a family-owned maker of leather travel bags and briefcases located in the northeastern part of the United States. Foreign competition has forced its owner, Heather Gray, to explore new ways to meet the competition. One of her cousins, Wallace Hayes, who recently graduated from college with a major in accounting, told her about the use of cost variance analysis to learn about efficiencies of production.

In May of last year, Heather asked Matt Jones, chief accountant, and Alfred Prudest, production manager, to implement a standard costing system. Matt and Alfred, in turn, retained Shannon Leikam, an accounting professor at Harding’s College, to set up a standard costing system by using information supplied to her by Matt’s and Alfred’s staff. To verify that the information was accurate, Shannon visited the plant and measured workers’ output using time and motion studies. During those visits, she was not accompanied by either Matt or Alfred, and the workers knew about Shannon’s schedule in advance. The cost system was implemented in June of last year.

Recently, the following dialogue took place among Heather, Matt, and Alfred:

HEATHER: How is the business performing?

ALFRED: You know, we are producing a lot more than we used to, thanks to the contract that you helped obtain from Lean, Inc., for laptop covers. (Lean is a national supplier of computer accessories.)

MATT: Thank goodness for that new product. It has kept us from sinking even more due to the inroads into our business made by those foreign suppliers of leather goods.

HEATHER: What about the standard costing system?

MATT: The variances are mostly favorable, except for the first few months when the supplier of leather started charging more.

HEATHER: How did the union members take to the standards?

ALFRED: Not bad. They grumbled a bit at first, but they have taken it in stride. We've consistently shown favorable direct labor efficiency variances and direct materials usage variances. The direct labor rate variance has been flat.

MATT: It should be since direct labor rates are negotiated by the union representative at the start of the year and remain the same for the entire year.

HEATHER: Matt, would you send me the variance report for laptop covers immediately?

The following chart summarizes the direct materials and direct labor variances from November of last year through April of this year (extracted from the report provided by Matt). Standards for each laptop cover are as follows:

Three feet of direct materials at $7.50 per foot.

Forty-five minutes of direct labor at $14 per hour.

Month Actual Cost
(Direct Materials
+ Direct Labor)
Direct Materials
Price Variance
Direct Materials
Efficiency
Variance
Direct Labor Rate
Variance
Direct Labor
Efficiency

Variance
November $150,000    $10,000    U $5,000    F $100    U $5,000 F
December 155,000    11,000    U 5,200    F 110    U 6,500 F
January 152,000    10,100    U 4,900    F 105    U 7,750 F
February 151,000    9,900    U 4,500    F 95    U 6,950 F
March 125,000    9,000    U 3,000    F 90    U 8,200 F
April 115,000    8,000    U 2,000    F 90    U 8,500 F

In addition, the data for May of this year, but not the variances for the month, are as follows:

Laptop covers made in May 2,900 units
Total actual direct materials costs incurred $ 68,850
Actual quantity of direct materials purchased and used 8,500 feet
Total actual direct labor cost incurred $ 25,910
Total actual direct labor hours 1,837.6 hours

Actual direct labor cost per hour exceeded the budgeted rate by $0.10 per hour.

Required:

For May of this year, calculate the price and quantity variances for direct labor and direct materials. Round intermediate calculations and final answers to two decimal places.

MPV $___________ Unfavorable
MUV $___________ Favorable
LRV $___________ Unfavorable
LEV $___________ Favorable

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...
Materials Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @ $4) $12.00 Direct labor (0.75 hr. @ $12) 9.00 Total prime cost $21.00 During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 299,500 strips at $3.30 per strip. There were no beginning or ending inventories of leather. Actual direct labor...
Global corporation has developed the following cost standards for the production of leather backpacks: Leather 0.9...
Global corporation has developed the following cost standards for the production of leather backpacks: Leather 0.9 yards x $22 per yard = $19.80 Direct labor 1.3 hours x $9.00 per hour = $11.70 Variable overhead 1.3 hours x $15.00 per hour = $19.50 Variable overhead is applied on the basis of direct labor hours. The actual results for last month were as follows: Number of backpacks produced 15,000 Direct labor hours incurred 18,800 Yards of leather purchased 14,500 Yards of...
Pato Company produces leather sandals. The company employs a standard costing system and has the following...
Pato Company produces leather sandals. The company employs a standard costing system and has the following standards in order to produce one pair of sandals: standard quantity standard price direct materials 2 leather strips ?? per strip direct labor 2.5 hours $12 per hour variable overhead 2.5 hours ?? per hour During May, Pato purchased leather strips at a total cost of $124,250 and had direct labor totaling $171,100. During May, Pato used 13,600 leather strips in the production of...
Budget Variances, Materials and Labor Cinturon Corporation produces high-quality leather belts. The company's plant in Boise...
Budget Variances, Materials and Labor Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (2 strips @ $6.00) $12.00 Direct labor (0.25 hr. @ $11.00) 2.75 Total prime cost $14.75 During the first month of the year, the Boise plant produced 31,000 belts. Actual leather purchased was 100,000 strips at $3.30 per strip. There were no beginning or ending inventories of leather....
Zee Corporation has developed the following cost standards for the production of its leather backpacks: Standard...
Zee Corporation has developed the following cost standards for the production of its leather backpacks: Standard Cost Per Backpack Leather (2.0 yards × $25 per yard) $50.00 Direct labor (2.3 hours × $10.00 per hour) $23.00 Variable overhead (2.3 hours × $16.00 per hour) $36.80 Variable overhead at Zee is applied on the basis of direct labor hours. The actual results for last month were as follows: Number of backpacks produced 12,500 Direct labor hours incurred 27,950 Yards of leather...
Pato Company produces leather sandals. The company employs a standard costing system and has the following...
Pato Company produces leather sandals. The company employs a standard costing system and has the following standards in order to produce one pair of sandals: standard quantity standard price direct materials 2 leather strips ?? per strip direct labor 2.5 hours $10 per hour variable overhead 2.5 hours ?? per hour During May, Pato purchased leather strips at a total cost of $124,520 and had direct labor totaling $117,100. During May, Pato used 18,790 leather strips in the production of...
Koontz Company manufactures a number of products. The standards relating to one of these products are...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit   Direct materials:      Standard: 1.80 feet at $2.20 per foot $ 3.96      Actual: 1.75 feet at $2.40 per foot $ 4.20      Direct labor:      Standard: 0.90 hours at $18.00 per hour 16.20      Actual: 0.95 hours at $17.40 per hour 16.53     Variable overhead:      Standard:...
Koontz Company manufactures a number of products. The standards relating to one of these products are...
Koontz Company manufactures a number of products. The standards relating to one of these products are shown below, along with actual cost data for May. Standard Cost per Unit Actual Cost per Unit Direct materials: Standard: 1.90 feet at $4.00 per foot $ 7.60 Actual: 1.85 feet at $4.40 per foot $ 8.14 Direct labor: Standard: 1.10 hours at $16.00 per hour 17.60 Actual: 1.15 hours at $15.40 per hour 17.71 Variable overhead: Standard: 1.10 hours at $9.00 per hour...
Materials and Labor Variances Horseco manufactures saddles.  The company set the following standards:  Leather per saddle:  10 feet. Cost...
Materials and Labor Variances Horseco manufactures saddles.  The company set the following standards:  Leather per saddle:  10 feet. Cost per foot:  $2.  In June, it manufactured 6,000 saddles.  The company used 58,000 feet of leather.  It purchased 70,000 feet of leather for $147,000.   Calculate the materials price and efficiency variances.   Kiteco makes kites.  Its standards are 2 hours of work at $30 per hour (including benefits) per kite. In March, employees worked 60,000 hours, made 32,000 kites and earned $1,725,000 in wages.  Calculate the labor rate and efficiency variances.  
Labor Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard...
Labor Variances Cinturon Corporation produces high-quality leather belts. The company's plant in Boise uses a standard costing system and has set the following standards for materials and labor: Leather (3 strips @ $4) $12.00 Direct labor (0.75 hr. @ $12) 9.00 Total prime cost $21.00 During the first month of the year, the Boise plant produced 92,000 belts. Actual leather purchased was 287,500 strips at $4.20 per strip. There were no beginning or ending inventories of leather. Actual direct labor...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT