Question

Kisler Incorporated makes a single product—a cooling coil used in commercial refrigerators. The company has a...

Kisler Incorporated makes a single product—a cooling coil used in commercial refrigerators. The company has a standard cost system in which it applies overhead to this product based on the standard machine-hours allowed for the actual output of the period. Data concerning the most recent year appear below:

Total budgeted manufacturing overhead $ 70,035
Budgeted production 15,000 units
Standard hours per unit (b) 0.70 machine-hours
Budgeted hours (a) × (b) 10,500 machine-hours
Actual production (a) 14,000 units
Standard hours per unit (b) 0.70 machine-hours
Standard hours allowed for the actual production (a) × (b) 9,800 machine-hours
Total actual manufacturing overhead $ 97,489

The predetermined overhead rate is closest to:

Homework Answers

Answer #1

Answer : 1)pre determined overhead rate is totally depends on estimations rather than the actuals

2) these manufacturing overheads are indirect costs associated with the product in the manufacturing overheads. These are depreciation on building and factory equipments and some salaries of factory employees , factory maintenance etc.

3) pre determined overhead rate is calculated with the following equation

= total budgeted manufacturing overhead cost / total budgeted machine hours

Total budgeted manufacturing overheads =$70,035 given

Total budgeted machine hours 10500 given

So

= $70,035/10500

=6.67

Pre determined overhead rate =6.67

Always pre determined overhead rate is calculated by using the budgeted information because ,it is related to the estimations rather than the actual.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Citi Company uses a standard cost system in which manufacturing overhead is applied to units of...
Citi Company uses a standard cost system in which manufacturing overhead is applied to units of product on the basis of standard machine-hours. During February, the company used a denominator activity of 60,000 machine-hours in computing its predetermined overhead rate. However, 75,000 standard machine-hours were allowed for the month's actual production. If the fixed manufacturing overhead volume variance for February was $6,800 unfavorable, then the total budgeted fixed manufacturing overhead cost for the month was (closest to ) Select one:...
Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost...
Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $4.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $1,764,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $9.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.20 per...
Problem 10A-8 Applying Overhead; Overhead Variances [LO10-3, LO10-4] Lane Company manufactures a single product and applies...
Problem 10A-8 Applying Overhead; Overhead Variances [LO10-3, LO10-4] Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $4.60 per direct labor-hour and the budgeted fixed manufacturing overhead is $1,935,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $9.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.30 per...
Wall Corporation, which produces commercial safes, has provided the following data: Budgeted production 9,300 safes Standard...
Wall Corporation, which produces commercial safes, has provided the following data: Budgeted production 9,300 safes Standard machine-hours per safe 8.0 machine-hours Standard supplies cost $   8.60 per machine-hour Actual production 9,500 safes Actual machine-hours 76,360 machine-hours Actual supplies cost $706,566 Supplies cost is an element of variable manufacturing overhead. The variable overhead rate variance for supplies is closest to: $52,966 U $49,870 F $52,966 F $49,870 U
The Clark Company makes a single product and uses standard costing. Some data concerning this product...
The Clark Company makes a single product and uses standard costing. Some data concerning this product for the month of May follow: Labour rate variance $7,000 favourable Labour efficiency variance $12,000 favourable Variable overhead efficiency variance $4,000 favourable Number of units produced 10,000 Standard labour rate per direct labour hour $12 Standard variable overhead rate per direct labour hour $4 Actual labour hours used 14,000 Actual variable manufacturing overhead costs $58,290 1) What was the variable overhead spending variance for...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $2.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $384,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $4.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.20 per hour. The company planned to operate at a...
chapter 9 h1 Problem 9A-8 Applying Overhead; Overhead Variances [LO9-6, LO9-7] Lane Company manufactures a single...
chapter 9 h1 Problem 9A-8 Applying Overhead; Overhead Variances [LO9-6, LO9-7] Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $5.60 per direct labor-hour and the budgeted fixed manufacturing overhead is $2,880,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $12.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...
10. Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 32,500 Total fixed manufacturing overhead cost $455,000 Variable manufacturing overhead per machine-hour $ 5.00 Recently, Job T687 was completed with the following characteristics: Number of units in the job 10 Total machine-hours 40 Direct materials $ 710 Direct labor cost $1,420 If the company marks...
1. Coles Corporation, Inc. makes and sells a single product, Product R. Three yards of Material...
1. Coles Corporation, Inc. makes and sells a single product, Product R. Three yards of Material K are needed to make one unit of Product R. Budgeted production of Product R for the next five months is as follows: August 14,000 units September 14,500 units October 15,500 units November 12,600 units December 11,900 units The company wants to maintain monthly ending inventories of Material K equal to 20% of the following month's production needs. On July 31, this requirement was...
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine       &n
Weller Company’s flexible budget for manufacturing overhead (in condensed form) follows:     Cost     Formula          (per machine         Machine-Hours   Overhead Costs            hour)  8,000    9,000    10,000 Variable costs   $1.05  $ 8,400 $ 9,450 $10,500 Fixed costs       24,800   24,800   24,800 Total Overhead Costs    $33,200 $34,250 $35,300 The following information is available for a recent period: a. The denominator activity of 8,000 machine-hours was chosen to compute the predetermined overhead rate. b. At the 8,000 standard machine-hours level of activity, the company should produce 3,200 units of product. c....
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT