Question

The Budgeted Cost of Work Performed (BCWP) is also known as “Earned Value.” It is a...

The Budgeted Cost of Work Performed (BCWP) is also known as “Earned Value.” It is a terminology widely used today to represent the dollar worth of all the project work that has been completed to date. Is it correct to call this the “Earned Value”? Has it really been earned? Give your views on the terminology, giving arguments both in favor of and against it.

Homework Answers

Answer #1

Budgeted Cost for Work Performed (BCWP) also called Earned Value (EV), is the budgeted cost of work that has actually been performed in carrying out a scheduled task during a specific time period. The BCWP is the sum of the budgets for completed work packages and completed portions of open work packages, plus the applicable portion of the budgets for level of effort and apportioned effort. so we can say it is earned value. Yes, it is really earned.in my view, the terminology is correct because actually what we perform will be measured as the budgeted cost of work performed and earned the value of work performed. We can also argue that the budgeted amount performed may not be equal to the actual amount earned, then we can not say both the terms are same.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
part 1) The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and...
part 1) The Budgeted Cost of the Work Scheduled (BCWS) comes from the cost-loaded schedule and is the budgeted or estimated cost for each of the tasks in the schedule that should have been completed or partially completed as of the date of selected. Group of answer choices true false part 2 Cost Performance Index (CPI) can be used a tool to project the total estimated project cost at completion. If a project's original estimate (budget) was $2,400,500 and the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
1. Which of the following statements is incorrect? a. The time value of money implies that...
1. Which of the following statements is incorrect? a. The time value of money implies that a dollar received today is worth more than a dollar received tomorrow. b. The time value of money implies that the further in the future you receive a dollar, the more it is worth today. c. All the answers are correct except one. d. A dollar today is worth more than a dollar received in the future. e. The earnings from compounding drive much...
The figure below depicts the schedule for a small project. The budgeted cost is shown within...
The figure below depicts the schedule for a small project. The budgeted cost is shown within the schedule bar for each activity. For the sake of simplicity, assume costs are distributed evenly throughout an activity's duration. For example, Activity A will take four weeks and has a total budgeted cost of $4,000. Consequently, expected expenditures for A will be $1,000 per week. In contrast, Activity B will cost $2,000 per week. Precedence relationships are as follows: A must precede B...
From the data shown below, calculate the earned value of each control account as of 5/30/19....
From the data shown below, calculate the earned value of each control account as of 5/30/19. Assume all control account work is on schedule except as noted below. Control Account Scheduled Start Scheduled Completion Budgeted Value EV Progress Rule 1 3/3/2019 6/30/2019 10,000 Percent Complete with Gates (Note 1) 2 5/5/2019 6/6/2019 3,000 Fixed Formula: 50/50 3 5/26/2019 6/6/2019 1,000 Fixed Formula: 0/100 4 5/12/2019 5/30/2019 2,000 Fixed Formula: 30/70 5 4/14/2019 7/11/2019 15,000 Weighted Milestones (Note 2) Note (1):...
For Sociology: Back in 1999, President Bill Clinton announced the commitment of $14 million to establish...
For Sociology: Back in 1999, President Bill Clinton announced the commitment of $14 million to establish an “Equal Pay Initiative.” Clinton explained his intention to take a proactive step to close the pay gap between men and women. At that time, women earned about seventy-five cents for every dollar earned by men. Comparable worth as a concept has always been controversial because it seeks to replace the economic market place with government regulations. Diana Furchtgott-Roth and Christine Stolba question the...
Land trusts, also known as conservancies, are not-for-profit organizations dedicated to protecting wildlife habitat and natural...
Land trusts, also known as conservancies, are not-for-profit organizations dedicated to protecting wildlife habitat and natural lands by acquiring ownership rights and transfer of development rights (conservation easements) either thru donation or purchase. This series of cases follows a small land trust through the process of budgeting. Case I requires students to develop and analyze an annual line-item budget and translate that budget, and additional information, into a quarterly cash budget. Case II requires students to convert the line-item budget...
Land trusts, also known as conservancies, are not-for-profit organizations dedicated to protecting wildlife habitat and natural...
Land trusts, also known as conservancies, are not-for-profit organizations dedicated to protecting wildlife habitat and natural lands by acquiring ownership rights and transfer of development rights (conservation easements) either thru donation or purchase. This series of cases follows a small land trust through the process of budgeting. Case I requires students to develop and analyze an annual line-item budget and translate that budget, and additional information, into a quarterly cash budget. Case II requires students to convert the line-item budget...
The project has been performing as planned, and the team members have been exhibiting increasing levels...
The project has been performing as planned, and the team members have been exhibiting increasing levels of trust between each other. The sponsor and the buyer have been satisfied with the delivery of business value, and user acceptance testing results are positive. A technical expert consulting with the team has expressed concerns that the team is not in agreement on the best way to deliver to the next review. If the project manager wants to support the team in reaching...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT