Question

On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job...

On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 54% of direct materials costs. During the month, the jobs used direct materials as shown below.

Job 1

Job 2

Job 3

Direct materials used

$6,400

$8,400

$2,900

During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the end of March, and Job 2 is finished but not sold by the end of March.

Job 1

Job 2

Job 3

Direct labor used

$9,300

$5,000

$4,000

1.

Determine the amounts of direct materials, direct labor, and factory overhead applied that would be reported on job cost sheets for each of the three jobs for March.

     

2.

Determine the total dollar amount of Work in Process Inventory at the end of March.

     

3.

Determine the total dollar amount of Finished Goods Inventory at the end of March. Assume the company has no beginning Work in Process or Finished Goods inventories.

Homework Answers

Answer #1
( A ) JOB 1($) JOB 2($) JOB 3($)
DIRECT MATERIAL 6400 8400 2900
DIRECT LABOUR 9300 5000 4000
OVERHEAD 3456 4536 1566
(54% OF D.M)
TOTAL COST 19156 17936 8466
( B ) WORK IN PROGRESS INVENTORY($) 19156        - 8466
( C ) FINISHED GOODS INVENTORY($)         - 17936           -
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job...
On March 1 a dressmaker starts work on three custom-designed wedding dresses. The company uses job order costing and applies overhead to each job (dress) at the rate of 40% of direct materials costs. During the month, the jobs used direct materials as shown below. Job 1 Job 2 Job 3 Direct materials used $ 5,000 $ 7,000 $ 1,500 During the month, the jobs used direct labor as shown below. Jobs 1 and 3 are not finished by the...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Balance on 3/1 Job 33 $ 4,400 Job 34 3,100 $ 7,500 Source documents revealed the following during March:          Materials Requisitions Forms Labor Time Tickets Status of Job at Month-End Job 33 $ 2,100 $ 4,300 Completed and sold Job 34 2,700 5,000...
Job 1 Job 2 Job 3 Direct Materials $6000 $3,400 $4,000 Direct Labor $1,800 $780 $600...
Job 1 Job 2 Job 3 Direct Materials $6000 $3,400 $4,000 Direct Labor $1,800 $780 $600 Machine Hours 28   24   12 Direct Labor Hours 75 32 25 A predetermined overhead rate of $180 per machine hour is used to apply manufacturing overhead. There was no beginning work-in-process inventory on March1. All three jobs were started during March. Job 2 was completed and sold during the month of March and Jobs 1 and 3 were still being worked on during the...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the...
Oak Creek Furniture Factory (OCFF), a custom furniture manufacturer, uses job order costing to track the cost of each customer order. On March 1, OCFF had two jobs in process with the following costs: Work in Process Balance on 3/1 Job 33 $ 6,000 Job 34 3,200 $ 9,200 Source documents revealed the following during March: Materials Requisitions Forms Labor Time Tickets Status of Job at Month-End Job 33 $ 3,700 $ 5,400 Completed and sold Job 34 3,800 4,000...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time,...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $7,000, direct labor of $4,200, and applied overhead of $3,570. Custom Cabinetry applies overhead at the rate of 85% of direct labor cost. During July, Job 120 is sold (on account) for $31,000, Job 121 is started and completed, and Job 122 is started and still in process at the end of the month. Custom Cabinetry...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating...
Job Costs, Ending Work in Process During March, Aragon Company worked on three jobs. Data relating to these three jobs follow:       Job 78       Job 79       Job 80 Units in each order 290   180         230   Units sold —   180         —   Materials requisitioned $1,740   $1,062         $2,507   Direct labor hours 319   198         345   Direct labor cost $3,509   $3,168         $3,312   Overhead is assigned on the basis of direct labor hours at a rate of $8.90 per...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate, Ending Balance of WIP, Finished Goods, and COGS At the beginning of March, Mendez Company had two jobs in process, Job 86 and Job 87, with the following accumulated cost information: Job 86 Job 87 Direct materials $4,800 $1,600 Direct labor 1,200 3,000 Applied overhead 888 2,220 Balance, March 1 $6,888 $6,820 During March, two more jobs (88 and 89) were started. The following direct materials and direct labor costs were added to...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time,...
Custom Cabinetry has one job in process (Job 120) as of June 30; at that time, its job cost sheet reports direct materials of $8,500, direct labor of $3,800, and applied overhead of $3,230. Custom Cabinetry applies overhead at the rate of 85% of direct labor cost. During July, Job 120 is sold (on account) for $25,500, Job 121 is started and completed, and Job 122 is started and still in process at the end of the month. Custom Cabinetry...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...