On March 1 a dressmaker starts work on three custom-designed
wedding dresses. The company uses job...
On March 1 a dressmaker starts work on three custom-designed
wedding dresses. The company uses job order costing and applies
overhead to each job (dress) at the rate of 40% of direct materials
costs. During the month, the jobs used direct materials as shown
below. Job 1 Job 2 Job 3 Direct materials used $ 5,000 $ 7,000 $
1,500 During the month, the jobs used direct labor as shown below.
Jobs 1 and 3 are not finished by the...
Johnson Company uses a job-order costing system and started the month of
March with three jobs...
Johnson Company uses a job-order costing system and started the month of
March with three jobs in process. The cost of beginning work in process
plus the costs added during March are shown below:
Job #1 Job #2 Job #3
beginning work in process ..... $4,930 $4,970 $2,840
COSTS ADDED DURING MARCH:
direct materials .............. $3,400 $4,200 $4,600
direct labor .................. $5,000 $4,000 ?
Johnson applies overhead to jobs based on a percentage of direct materials
used. During March, Johnson...
Oak Creek Furniture Factory (OCFF), a custom furniture
manufacturer, uses job order costing to track the...
Oak Creek Furniture Factory (OCFF), a custom furniture
manufacturer, uses job order costing to track the cost of each
customer order. On March 1, OCFF had two jobs in process with the
following costs:
Work in Process
Balance on 3/1
Job 33
$
4,400
Job 34
3,100
$
7,500
Source documents revealed the following during
March:
Materials Requisitions Forms
Labor Time Tickets
Status of Job at Month-End
Job 33
$
2,100
$
4,300
Completed and sold
Job 34
2,700
5,000...
Job 1 Job 2 Job 3
Direct Materials $6000 $3,400 $4,000
Direct Labor $1,800 $780 $600...
Job 1 Job 2 Job 3
Direct Materials $6000 $3,400 $4,000
Direct Labor $1,800 $780 $600
Machine Hours 28 24 12
Direct Labor Hours 75 32 25
A predetermined overhead rate of $180 per machine hour is used
to apply manufacturing overhead.
There was no beginning work-in-process inventory on March1. All
three jobs were started during March. Job 2 was completed and sold
during the month of March and Jobs 1 and 3 were still being worked
on during the...
Oak Creek Furniture Factory (OCFF), a custom furniture
manufacturer, uses job order costing to track the...
Oak Creek Furniture Factory (OCFF), a custom furniture
manufacturer, uses job order costing to track the cost of each
customer order. On March 1, OCFF had two jobs in process with the
following costs:
Work in Process
Balance on 3/1
Job 33
$
6,000
Job 34
3,200
$
9,200
Source documents revealed the following during March:
Materials Requisitions Forms
Labor Time Tickets
Status of Job at Month-End
Job 33
$
3,700
$
5,400
Completed and sold
Job 34
3,800
4,000...
Custom Cabinetry has one job in process (Job 120) as of June 30;
at that time,...
Custom Cabinetry has one job in process (Job 120) as of June 30;
at that time, its job cost sheet reports direct materials of
$7,000, direct labor of $4,200, and applied overhead of $3,570.
Custom Cabinetry applies overhead at the rate of 85% of direct
labor cost. During July, Job 120 is sold (on account) for $31,000,
Job 121 is started and completed, and Job 122 is started and still
in process at the end of the month. Custom Cabinetry...
Job Costs, Ending Work in Process
During March, Aragon Company worked on three jobs. Data relating...
Job Costs, Ending Work in Process
During March, Aragon Company worked on three jobs. Data relating
to these three jobs follow:
Job 78
Job 79
Job 80
Units in each order
290
180
230
Units sold
—
180
—
Materials requisitioned
$1,740
$1,062
$2,507
Direct labor hours
319
198
345
Direct labor cost
$3,509
$3,168
$3,312
Overhead is assigned on the basis of direct labor hours at a
rate of $8.90 per...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate,
Ending Balance of WIP, Finished Goods, and COGS
At...
Prepare Job-Order Cost Sheets, Predetermined Overhead Rate,
Ending Balance of WIP, Finished Goods, and COGS
At the beginning of March, Mendez Company had two jobs in
process, Job 86 and Job 87, with the following accumulated cost
information:
Job 86
Job 87
Direct materials
$4,800
$1,600
Direct labor
1,200
3,000
Applied overhead
888
2,220
Balance, March 1
$6,888
$6,820
During March, two more jobs (88 and 89) were started. The
following direct materials and direct labor costs were added to...
Custom Cabinetry has one job in process (Job 120) as of June 30;
at that time,...
Custom Cabinetry has one job in process (Job 120) as of June 30;
at that time, its job cost sheet reports direct materials of
$8,500, direct labor of $3,800, and applied overhead of $3,230.
Custom Cabinetry applies overhead at the rate of 85% of direct
labor cost. During July, Job 120 is sold (on account) for $25,500,
Job 121 is started and completed, and Job 122 is started and still
in process at the end of the month. Custom Cabinetry...