Question

The following information is available pertaining to the Production Division of Clarkson Enterprises: Assembly Dept.      ...

The following information is available pertaining to the Production Division of Clarkson Enterprises:

Assembly Dept.       Finishing Dept.        Total

Overhead costs                 $10,000        $30,000               $40,000

Direct labor hours 8,000           2,000                    10,000

Machine hours                 3,000           5,000                      8,000

Production information pertaining to Job 4X5:

Assembly Dept.       Finishing Dept.        Total

Prime costs           $2,380                    $-0-                        $2,380

Direct labor hours    280                         -0-                          280

Machine hours        -0-                           -0-                           -0-

Units produced       500                         -0-                           500

1. Refer to Figure 5-7. What is the plantwide overhead rate based on direct labor hours?

a. $1.00

b. $1.50

c. $3.00

d. $4.00

2. Refer to Figure 5-7. Using the plantwide overhead rate based on direct labor hours what is the cost of Job 4X5?

a. $1,250

b. $2,000

c. $8,750

d. $3,500

3. Refer to Figure 5-7. What is the overhead rate for the Finishing Department based on machine hours?

a. $6.00

b. $4.00

c. $2.25

d. $1.50

4. Refer to Figure 5-7. What are the total overhead costs assigned to Job 4X5, assuming the Assembly and Finishing Departments use direct labor hours and machine hours for their bases, respectively?

a. $62.50

b. $250.00

c. $350.00

d. $2,380.00

Figure 5-4

Lanyard Company uses a job-order costing system to account for product costs. The following information pertains to 2014:

Materials placed into production           $170,000

Indirect labor                                                              40,000

Direct labor (10,000 hours)                               160,000

Depreciation of factory building              60,000

Other factory overhead                                    100,000

Increase in work-in-process inventory     20,000

Factory overhead rate is $20 per direct labor hour.

5. Refer to Figure 5-4. What is the total amount credited to Materials Inventory for Lanyard in 2014?

a. $480,000

b. $170,000

c. $140,000

d. $110,000

6. Refer to Figure 5-4. What is the total amount debited to Finished Goods Inventory in 2011?

a. $490,000

b. $510,000

c. $450,000

d. $550,000

Homework Answers

Answer #1
Q1.
Answer is d. $4
Explanation:
Estimated overheads 40000
Divide: Labour hours 10000
OH rate per DLH 4
Q2.
Answer is d. $ 3500
Explanation:
Cost of Job 4X5
Prime Cost 2380
Oh (280 hrs @4) 1120
Total cost 3500
Q3.
Answer is a. $ 6.00
Explanation:
Estimated OH of finished deptt 30000
Divide: machine hours 5000
OH rate per MH 6
Q4.
Answer is c. $ 350
Explanation:
Assembly Oh (280*1.25 per DLH) 350
Finishing 0
Total OH cost of Job 4X5 350
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following information is available pertaining to the Production Division of Clarkson Enterprises: Assembly Dept. Finishing...
The following information is available pertaining to the Production Division of Clarkson Enterprises: Assembly Dept. Finishing Dept. Total Overhead costs $10,000 $30,000 $40,000 Direct labor hours 8,000 2,000 10,000 Machine hours 3,000 5,000 8,000 Production information pertaining to Job 4X5: Assembly Dept. Finishing Dept. Total Prime costs $2,380 $-0- $2,380 Direct labor hours 280 -0- 280 Machine hours -0- -0- -0- Units produced 500 -0- 500 1. Refer to Figure 5-7. What is the plant wide overhead rate based on...
Tracey Company of Cincinnati, Ohio has two manufacturing departments—Machining and Assembly. The company considers all of...
Tracey Company of Cincinnati, Ohio has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $500,000 $100,000 $600,000 Direct labor-hours 10,000 50,000 60,000 Machine-hours 50,000 5,000 55,000 Job A Machining Assembly Total Direct labor-hours 5 10 15 Machine-hours 11 2...
Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly Finishing Manufacturing overhead...
Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly Finishing Manufacturing overhead costs $ 1,120,800 $ 510,000 Direct labor hours 11,100 DLH 19,100 DLH Machine hours 5,100 MH 15,100 MH 1. What is the company's single overhead rate based on direct labor hours? Estimated overhead costs       per direct labor hour Estimated direct labor hours 2. What is the company's single plantwide overhead rate base on machine hours? Estimated overhead costs per machine hour Estimated...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 500,000 $ 100,000 $ 600,000 Direct labor hours 10,000 50,000 60,000 Machine hours 50,000 5,000 55,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 7,056,000 $ 441,000 $ 7,497,000 Direct labor-hours 21,000 336,000 357,000 Machine-hours 336,000 16,000 352,000 Job A Machining Assembly Total Direct labor-hours 5 10 15 Machine-hours 11 2...
Wilmington Company has two manufacturing departments—Assembly and Fabrication. It considers all of its manufacturing overhead costs...
Wilmington Company has two manufacturing departments—Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year—Job Bravo. Estimated Data Assembly Fabrication Total Manufacturing overhead costs $ 2,850,000 $ 3,230,000 $ 6,080,000 Direct labor-hours 95,000 57,000 152,000 Machine-hours 38,000 190,000 228,000 Job Bravo Assembly...
Required information [The following information applies to the questions displayed below.]    Angle Max Industries produces...
Required information [The following information applies to the questions displayed below.]    Angle Max Industries produces a product which goes through two operations, Assembly and Finishing, before it is ready to be shipped. Next year’s expected costs and activities are shown below. Assembly Finishing Direct labor hours 160,000 DLH 146,000 DLH Machine hours 360,000 MH 82,800 MH Overhead costs $ 360,000 $ 525,600 Assume that the Assembly Department allocates overhead based on machine hours, and the Finishing Department allocates overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 9,522,000 $ 529,000 $ 10,051,000 Direct labor hours 23,000 414,000 437,000 Machine hours 414,000 18,000 432,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 18,032,000 $ 784,000 $ 18,816,000 Direct labor hours 28,000 644,000 672,000 Machine hours 644,000 23,000 667,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs...
Wilmington Company has two manufacturing departments--Assembly and Fabrication. It considers all of its manufacturing overhead costs to be fixed costs. The first set of data that is shown below is based on estimates from the beginning of the year. The second set of data relates to one particular job completed during the year--Job Bravo. Estimated Data Assembly Fabrication Total Manufacturing overhead costs $ 3,200,000 $ 3,600,000 $ 6,800,000 Direct labor-hours 100,000 60,000 160,000 Machine-hours 40,000 200,000 240,000 Job Bravo Assembly...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT