On January 6, 2019, Baxter Company purchased a site for a new manufacturing plant for $2,900,000. At a cost of $18,500, it razed an existing facility (fair market value $250,000) and received $12,000 from its salvage. The company also paid $6,900 in attorney fees, $2,100 in inspection fees, and $1,400 for a permit to raze the facility. After the facility was torn down, the following costs were incurred: $55,400 for fill dirt for the site, $37,000 for leveling the site, $130,000 for paving sidewalks and curbs, and $4,700,000 for building costs of the new facility. The parking area was paved at a cost of $130,700. Required: 1-3. Compute the capitalized cost of the manufacturing plant, land and land improvements. On January 6, 2019, Baxter Company purchased a site for a new manufacturing plant for $2,900,000. At a cost of $18,500, it razed an existing facility (fair market value $250,000) and received $12,000 from its salvage. The company also paid $6,900 in attorney fees, $2,100 in inspection fees, and $1,400 for a permit to raze the facility. After the facility was torn down, the following costs were incurred: $55,400 for fill dirt for the site, $37,000 for leveling the site, $130,000 for paving sidewalks and curbs, and $4,700,000 for building costs of the new facility. The parking area was paved at a cost of $130,700. Required: 1-3. Compute the capitalized cost of the manufacturing plant, land and land improvements.
Baxter Company
Capitalized cost of manufacturing facility $4,700,000
Cost of land acquisition |
$2,900,000 |
|
Add: cost of razing old building |
$18,500 |
|
value of salvaged materials |
($12,000) |
|
permit to raze |
$1,400 |
$7,900 |
Add: Attorney fee |
$6,900 |
|
Insurance cost |
$2,100 |
|
Cost of land |
$2,916,900 |
Cost of land improvements |
|
cost of filling the site |
55,400 |
cost of leveling the site |
$37,000 |
sidewalks and curbs |
$130,000 |
cost of paving parking area |
$130,700 |
cost of land improvements |
$253,100 |