Question

Brenton Chair's cost formula for its supplies cost is $1,620 per month plus $13 per chair....

Brenton Chair's cost formula for its supplies cost is $1,620 per month plus $13 per chair. For the month of April, the company planned for activity of 882 chairs, but the actual level of activity was 878 chairs. The actual supplies cost for the month was $13,500. The supplies cost in the flexible budget for April would be closest to:

Homework Answers

Answer #1

The supplies cost in the flexible budget for April would be closest to:

$ 466 Unfavorable

Working:

Step-1:Calculation of Standard cost
Standard cost = Fixed cost+Variabel cost per unit*Number of units in the month
= $       1,620 + 878 * $          13
= $     13,034
Step-2:Calculation of activity variance
Standard cost $     13,034
Actual cost $     13,500
Difference in cost $ 466 Unfavorable
Since Actual cost is in excess of Standard cost, it is $ 466 Unfavorable Variance.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Larance Detailing's cost formula for its materials and supplies is $1,870 per month plus $6 per...
Larance Detailing's cost formula for its materials and supplies is $1,870 per month plus $6 per vehicle. For the month of November, the company planned for activity of 82 vehicles, but the actual level of activity was 47 vehicles. The actual materials and supplies for the month was $2,250. The materials and supplies in the flexible budget for November would be closest to:
Sigler Lube's cost formula for its supplies cost is $1,150 per month plus $11 per oil...
Sigler Lube's cost formula for its supplies cost is $1,150 per month plus $11 per oil change. For the month of May, the company planned for activity of 789 oil changes, but the actual level of activity was 792 oil changes. The actual supplies cost for the month was $9,480. The spending variance for supplies cost in May would be: a.$382 F b.$349 U c.$349 F d.$382 U The Baskell Surgery Center's cost formula for its payroll is $1,220 per...
Jonathan Yardlighting's cost formula for its supplies cost is $1,230 per month plus $10 per light....
Jonathan Yardlighting's cost formula for its supplies cost is $1,230 per month plus $10 per light. For the month of November, the company planned for activity of 592 lights, but the actual level of activity was 597 lights. The actual supplies cost for the month was $7,050. The activity variance for supplies cost in November would be closest to:
Shelby Boat Wash's cost formula for its cleaning equipment and supplies is $2,940 per month plus...
Shelby Boat Wash's cost formula for its cleaning equipment and supplies is $2,940 per month plus $35 per boat. For the month of September, the company planned for activity of 73 boats, but the actual level of activity was 29 boats. The actual cleaning equipment and supplies for the month was $4,010. The spending variance for cleaning equipment and supplies in September would be closest to: $1,485U $55 F $55 U $1,485 F
Mondo Snow Removal's cost formula for its vehicle operating cost is $1,220 per month plus $657...
Mondo Snow Removal's cost formula for its vehicle operating cost is $1,220 per month plus $657 per snow-day. For the month of January, the company planned for activity of 26 snow-days, but the actual level of activity was 30 snow-days. The actual vehicle operating cost for the month was $20,520. The activity variance for vehicle operating cost in January would be closest to: $2,218F $2,628U $2,218U $2,628F
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 2,600 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 2,600 machine-hours Variable overhead costs: Supplies $ 11,960 Indirect labor 22,100 Fixed overhead costs: Supervision 15,600 Utilities 6,000 Depreciation 7,000 Total overhead cost $ 62,660 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 2,500 machine-hours rather than 2,600 machine-hours? Multiple Choice $60,750 $60,250 $61,350 $62,660 . Petrus Framing's cost...
16) Biden Corporation is an oil well service company that measures its output by the number...
16) Biden Corporation is an oil well service company that measures its output by the number of wells serviced. The company has provided the following fixed and variable cost estimates that it uses for budgeting purposes. Fixed Element per Month Variable Element per Well Serviced Revenue $ 4,700 Employee salaries and wages $ 41,300 $ 1,000 Servicing materials $ 600 Other expenses $ 40,200 When the company prepared its planning budget at the beginning of May, it assumed that 29...
Item 20 The Charade Corporation is preparing its Manufacturing Overhead budget for the fourth quarter of...
Item 20 The Charade Corporation is preparing its Manufacturing Overhead budget for the fourth quarter of the year. The budgeted variable manufacturing overhead is $4 per direct labor-hour; the budgeted fixed manufacturing overhead is $84,000 per month, of which $15,900 is factory depreciation. If the budgeted direct labor time for November is 7,900 hours, then the total budgeted manufacturing overhead for November is: Multiple Choice $84,000 $99,700 $131,500 $115,600 20B. Dermody Snow Removal's cost formula for its vehicle operating cost...
Im struggling with the U and F problems if you could can you please go over...
Im struggling with the U and F problems if you could can you please go over both thank you! Dubberly Corporation's cost formula for its manufacturing overhead is $31,700 per month plus $54 per machine-hour. For the month of March, the company planned for activity of 8,120 machine-hours, but the actual level of activity was 7,990 machine-hours. The actual manufacturing overhead for the month was $493,910. The spending variance for manufacturing overhead in March would be closest to: Multiple Choice...
Birkner Corporation's flexible budget performance report for last month shows that actual indirect materials cost, a...
Birkner Corporation's flexible budget performance report for last month shows that actual indirect materials cost, a variable cost, was $30,444 and that the spending variance for indirect materials cost was $8,142 favorable. During that month, the company worked 17,700 machine-hours. Budgeted activity for the month had been 18,200 machine-hours. The cost formula per machine-hour for indirect materials cost must have been closest to: Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 2,400 machine-hours Variable...