Proposal A: | |
AW of first cost = -650000*0.05*1.05^10/(1.05^10-1) = | $ -84,178 |
Annual operating cost | $ -1,70,000 |
AW of salvage value = 17000*0.05/(1.05^10-1) = | $ 1,352 |
AW of proposal | $ -2,52,826 |
Answer: [B] [Difference in solution due to rounding off difference] | |
Proposal B: | |
AW = -4000000*5%-5000 = | $ -2,05,000 |
Answer: [A] |