Bay City Company’s fixed budget performance report for July
follows. The $594,000 budgeted total expenses include $450,000
variable expenses and $144,000 fixed expenses. Actual expenses
include $134,000 fixed expenses.
Fixed Budget | Actual Results | Variances | ||||||||
Sales (in units) | 8,100 | 7,000 | ||||||||
Sales (in dollars) | $ | 648,000 | $ | 623,000 | $ | 25,000 | U | |||
Total expenses | 594,000 | 556,000 | 38,000 | F | ||||||
Income from operations | $ | 54,000 | $ | 67,000 | $ | 13,000 | U | |||
Prepare a flexible budget performance report that shows any
variances between budgeted results and actual results. List fixed
and variable expenses separately. (Indicate the effect of
each variance by selecting for favorable, unfavorable, and no
variance. Do not round your intermediate calculations. Round your
final answers to whole dollars.)