Question

The Garden of Eden Company produces three products: Adam, Eve and Serpent. The company uses a...

The Garden of Eden Company produces three products: Adam, Eve and Serpent. The company uses a normal cost system and overhead costs are currently charged to products using a plant-wide overhead rate based on machine hours. Because of considerable differences in the support cost needs of each product, it is probably advisable that the company switch to an activity-based costing system to charge overhead to products.

The company expects to produce 1,000 Adams, 3,400 Eves, and 600 Serpents in fiscal year 2019. Each Adam requires 20 direct labor hours and 43 machine hours, Eves require 50 direct labor hours and 30 machine hours, and Serpents require 80 direct labor hours and 25 machine hours. The total direct labor hours and total machine hours the company expects to operate next year are 238,000 direct labor hours and 160,000 machine hours.

Budgeted (Estimated) Overhead Data For 2019:

Machine

Engineering

Inspect. &

Total

Item

Setups

Changes

Packing

Overhead $’s

Overhead Dollars:

$170,000

$320,000

$470,000

$960,000

Activity Levels:

34 setups

400 Changes

5,000 units

Based on an analysis of the three overhead activities, it was estimated that the three products would require these activities as follows in fiscal year 2019:

Overall

Activity

Adam

Eve

Serpent

Totals

Machine Setups

5 setups

9 setups

20 setups

34 setups

Engineering Changes

140 changes

8 changes

252 changes

400 changes

Inspection & Packing*

1,000 units

3,400 units

600 units

5,000 units

*All units of each product are individually inspected and packed.

The direct material and direct labor costs included in the three products are as follows:

Item

Adam

Eve

Serpent

Direct Material (per unit)

$680

$300

$730

Direct Labor (per unit)

$900

$560

$850

Required:

a. Calculate the cost of each product using a plant-wide overhead rate based on machine hours.

b. Calculate the activity cost rates for (1) setups, (2) engineering changes and (3) inspection and packing.

c. Cost out the three products using an activity-based costing system.

d. Explain whether the normal costing system (in question 1) or the activity-based system (in question 2) is a better choice for the Garden of Eden.

Homework Answers

Answer #1

a. Cost of Each Product using Plant-wide OH Rate

Plant-Wide OH Rate = Total Overheads / Total Machine Hours = $960000 / 160000 = $6 per Machine Hour

b. Computation of Activity Cost rates

Machine Setups = Total Setup OH / Total Setups = $170000 / 34 = $5000 per Setup

Engineering Changes = Total Engineering changes OH / Total Engineering Changes = $320000 / 400 = $800 per Change

Inspection and Packing = Total I&P OH / Total I&P = $470000 / 5000 = $94 per Unit

c. Cost of Three products

d. ABC system is obviously a better in case of multiple products produced by the company as it helps in tracing of OH costsand will accurate product cost and will eventually helps in better decision making and cost management

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Marion Manufacturing uses an activity-based costing system. The company produces Model X and Model Y. Information...
Marion Manufacturing uses an activity-based costing system. The company produces Model X and Model Y. Information relating to the two products is as follows: Model X Model Y Units produced 20,000 40,000 Machine hours 8,000 10,000 Direct labor hours 14,000 16,000 Engineering labor (hours) 1,000 1,400 Setups 40 60 The following costs are reported: Engineering $ 48,000 Setups 100,000 Machine-related overhead 144,000 Machine-related overhead would be classified as a a.unit-level activity. b.facility-level activity. c.batch-level activity. d.product-level activity.
Assume a company produces and sells only two products—14,000 units of Product A and 6,000 units...
Assume a company produces and sells only two products—14,000 units of Product A and 6,000 units of Product B. The selling prices are $65 per unit for Product A and $96 per unit for Product B. Product A’s direct materials and direct labor costs per unit are $32 and $12, respectively. Product B’s direct materials and direct labor costs per unit are $34 and $15, respectively. The company is considering implementing an activity-based costing (ABC) system that allocates all of...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $748,800 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 206,000 10,000...
Aresco Corporation manufactures two products: Product G51B and Product E48X. The company uses a plantwide overhead...
Aresco Corporation manufactures two products: Product G51B and Product E48X. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products G51B and E48X. Activity Cost Pool Activity Measure Total Cost Total Activity Machining Machine-hours $100,000 5,000 MHs Machine setups Number of setups $300,000 500...
Lenoir Company manufactures two products—28,000 units of Product D and 12,000 units of Product R. The...
Lenoir Company manufactures two products—28,000 units of Product D and 12,000 units of Product R. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products D and R: Activity Cost Pool Activity Measure        Estimated Overhead Cost Expected Activity Machining. . . . ....
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.50 25,000 units Sprockets 0.10 41,000 units Additional information about the company follows: a. Hubs require $28 in direct materials per unit, and Sprockets require $12. b. The direct labor wage rate is $19 per hour. c. Hubs are more complex to manufacture than Sprockets and they require special processing. d. The company’s activity-based absorption costing system has the...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $732,100 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 209,000 10,000...
Please explain how to get the following answer from this question: Vandalay Industries manufactures two​ products:...
Please explain how to get the following answer from this question: Vandalay Industries manufactures two​ products: toasters and blenders. The annual production and sales of toasters is 2,100 units, while 1,600 units of blenders are produced and sold. The company has traditionally used direct labor hours to allocate its overhead to products. Toasters require 1.25 direct labor hours per​ unit, while blenders require 1 direct labor hours per unit. The total estimated overhead for the period is $147,215. The company...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours...
Fogerty Company makes two products—titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit Annual Production Hubs 0.60 22,000 units Sprockets 0.20 55,000 units Additional information about the company follows: a. Hubs require $35 in direct materials per unit, and Sprockets require $17. b. The direct labor wage rate is $19 per hour. c. Hubs are more complex to manufacture than Sprockets and they require special processing. d. The company’s activity-based absorption costing system has the...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:    Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity   Machining Machine-hours $ 200,000   ...