Question

Madtack Company uses a job-order costing system and started the month of March with only one...

Madtack Company uses a job-order costing system and started the month
of March with only one job in process (Job #359). This job had $5,000
of total cost assigned to it at the beginning of March. Madtack applies
overhead to jobs at a rate of 175% of direct labor cost. During March,
Madtack assigned production costs as follows to the jobs worked on
during the month:

                             Job #359      Job #360      Job #361
direct materials ..........   $1,000         $5,000       $3,000
direct labor ..............    2,000          3,000        2,000

During March, Madtack completed and sold Job #360. Job #361 was also
completed but was not sold by the end of March. Job #359 was not
completed by the end of March. Madtack Company had total actual
overhead cost of $10,700 for the month of March. 

Calculate the cost of goods sold reported by Madtack for March after
the overhead variance has been closed.

Homework Answers

Answer #1
Job Cost sheet
Job 359 Job 360 Job 361 Total
Beginning Cost of WIP 5000 5000
Direct Material 1000 5000 3000 9000
Direct Labour 2000 3000 2000 7000
Oh applied (175% of DLC) 3500 5250 3500 12250
Total cost of Jobs 11500 13250 8500 33250
Status WIP Sold FG
Under/Over applied Overheads
Actual Overheads incurred 10700
Less: Overheads applied 12250
Over-applied Overheads 1550
Cost of Good sold:
Cost of job 360 sold 13250
Less: Over-applied Overheads 1550
Adjusted Cost of Good ssold 11700
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Madtack Company uses a job-order costing system and started the month of March with only one...
Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor...
Johnson Company uses a job-order costing system and started the month of March with three jobs...
Johnson Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #1 Job #2 Job #3 beginning work in process ..... $4,930 $4,970 $2,840 COSTS ADDED DURING MARCH: direct materials .............. $3,400 $4,200 $4,600 direct labor .................. $5,000 $4,000 ? Johnson applies overhead to jobs based on a percentage of direct materials used. During March, Johnson...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials ....... $98,000 $75,000 $91,000 direct labor cost ...... $95,200 $79,900 $69,700 direct labor hours ..... 5,600 4,700 4,100 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor...
Jackson Company applies overhead to products using a pre determined rate of $12.10 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials ....... $98,000 $75,000 $91,000 direct labor cost ...... $95,200 $79,900 $69,700 direct labor hours ..... 5,600 4,700 4,100 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the...
Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour....
Jackson Company applies overhead to products using a pre-determined rate of $11.20 per direct labor hour. During 2019, Jackson Company began work on three jobs. Information relating to these three jobs appears below: Job #359 Job #360 Job #361 direct materials .............. $98,000 $75,000 $91,000 direct labor cost ............. $98,600 $79,900 $86,700 direct labor hours ............ 5,800 4,700 5,100 By the end of 2019, job #359 and job #361 had been completed. Job #360 was not completed by the end...
Johnson Company applies overhead to products using direct labor hours as the activity level. During 2019,...
Johnson Company applies overhead to products using direct labor hours as the activity level. During 2019, Johnson Company had the following estimated costs: Direct materials .................... $278,000 Direct labor ........................ 255,000 (15,000 hours expected) Advertising ......................... 37,000 Rent on factory building ............ 38,000 Depreciation .................... ... 60,000 Indirect materials .................. 20,000 Sales commissions ................... 40,000 Production supervisor's salary ...... 50,000 Insurance on factory equipment ...... 18,000 CEO's salary ........................ 95,000 The following additional information is available: 1. 30% of the...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide rate of 90% of direct materials cost. Br3-Pf Company began work on four jobs during June. Information related to the four jobs appears below: Job #1 Job #2 COSTS ADDED DURING JUNE direct materials .............. $5,800 $7,500 direct labor .................. $7,300 $6,300 Job #3 Job #4 COSTS ADDED DURING JUNE direct materials .............. $8,200 $6,400 direct labor .................. $7,920 $7,560 By the end of...
Waldbauer Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed...
Waldbauer Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed out to cost of goods sold at the end of the month. In October the company completed job N66B that consisted of 10,000 units of one of the company's standard products. No other jobs were in process during the month. The job cost sheet for job N66B shows the following costs: Beginning balance $ 41,000 Direct materials $251,000 Direct labor cost $ 98,000 Manufacturing...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q.
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...