Question

Suppose that the variable production overhead cost of a product is as follows: 4 hours at...

Suppose that the variable production overhead cost of a product is as follows:

4 hours at $3 = $12per unit.

During the period, 5,000 units of the product were made. The labour worked 6,050 hours of which 90 hours were recorded as idle time. The Variable overhead cost was $20,000.

Calculate the following variances:

  1. The variable overhead total variance
  2. The Variable production overhead Expenditure Variance
  3. The Variable production overhead Efficiency Variance.

Homework Answers

Answer #1

Standard hours to produce 5000 units =actuai units * standard hrs per unit =5000*4=20000

Standard cost for 5000 units =Standard hrs for 5000 units * standard rate per unit = 20000*3 = 60000

Actual per hr overhead rate =Actul overhead/actual hrs of production = 20000/6050=3.3057

Efficiency Variance :

(actual labor hours less budgeted labor hours) x hourly rate for standard variable overhead

=(6050-20000)*3 =41850 Favourable

Expenditure variance :

(actual labor rate less budgeted labor rate) x Actual hrs worked

=(3.3057-3)*6050 = 1850 Adverse

Total overhead variance =

=Expenditure variance + Efficiency variance

or

= Actual cost - Standard Cost

=20000-60000(workings on the top) or 41850-1850

= 40000 Favourable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,900 units. Manufacturing overhead is budgeted at $124,600 for the period (20% of this cost is fixed). The 16,830 hours worked during the period resulted in the production of 8,240 units. The variable manufacturing overhead cost incurred was $101,200 and the fixed manufacturing overhead cost was $28,900. a.Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
Question 1 A company manufactures a single product for which the standard variable cost is:                            
Question 1 A company manufactures a single product for which the standard variable cost is:                                                                          K per unit Direct material: 81 kg x K7 per kg                            567 Direct labour:    97 hours x K8 per hour                   776 Variable overhead: 97 hours x K3 per hour              291                                                                                1,634 Budget Sales and production volume                   81,600 units Standard selling price                               K59 per unit Standard variable cost                             K24 per unit During January, 530 units were produced and the costs incurred were as follows:...
Draco, Inc. has the following overhead standards: Variable overhead: 4 hours at $8 per hour Fixed...
Draco, Inc. has the following overhead standards: Variable overhead: 4 hours at $8 per hour Fixed overhead: 4 hours at $10 per hour The standards were based on a planned activity of 20,000 machine hours when 5,000 units were scheduled for production. Actual data follow. Variable overhead incurred: $167,750 Fixed overhead incurred: $210,000 Machine hours worked: 19,800 Actual units produced: 5,100 Duncanville’s fixed-overhead volume variance is: Duncanville’s variable-overhead efficiency variance is: The amount of variable overhead that Duncanville applied to...
1) MNO produces a single product. The standard production requirement for each unit requires 0.50 direct...
1) MNO produces a single product. The standard production requirement for each unit requires 0.50 direct labour hours at a standard rate of $11 per hour. During the last year, MNO assembly line workers worked a total of 5,000 hours at a cost of $50,000 to MNO. Also last year, MNO manufactured 3,000 units of product. What was the company's direct labour rate variance for the year? 2) MNO produces a single product. The standard production requirement for each unit...
FBC(Pty) manufactures one product, Product X. You were given the following information for period 4. Product...
FBC(Pty) manufactures one product, Product X. You were given the following information for period 4. Product X has a standard material cost as follows. 10kg of material Y at P10 per kg =P100 per unit of X. During period 4, 1000 units of X were manufactured using 11700 kg of material Y which cost P98631. The standard labour cost of product X is as follows, 2 hours of grade Z labour at P10 per hour=P20 per unit of product X....
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $10 per pound $ 50 Direct labor: 4 hours at $16 per hour 64 Variable overhead: 4 hours at $7 per hour 28 Total standard cost per unit $ 142 The planning budget for March was based on producing and selling 20,000 units. However, during March the company...
Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours...
Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows: Direct materials: 5 pounds at $10 per pound $ 50 Direct labor: 4 hours at $16 per hour 64 Variable overhead: 4 hours at $7 per hour 28 Total standard cost per unit $ 142 The planning budget for March was based on producing and selling 20,000 units. However, during March the company actually...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct...
Preble Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labour-hours, and its standard costs per unit are as follows: Direct materials: 6 kg at $8.00 per kg $ 48.00 Direct labour: 3 hours at $14 per hour 42.00 Variable overhead: 3 hours at $5 per hour 15.00 Total standard cost per unit $ 105.00 The company planned to produce and sell 19,000 units in March. However, during March the company actually produced and...