Question

CASE 3–18 Ethics and the Manager [Course Objective B] Terri Ronsin had recently been transferred to...

CASE 3–18 Ethics and the Manager [Course Objective B] Terri Ronsin had recently been transferred to the Home Security Systems Division of National Home Products. Shortly after taking over her new position as divisional controller, she was asked to develop the division’s predetermined overhead rate for the upcoming year. The accuracy of the rate is important because it is used throughout the year and any overapplied or underapplied over- head is closed out to Cost of Goods Sold at the end of the year. National Home Products uses direct labor-hours in all of its divisions as the allocation base for manufacturing overhead.

To compute the predetermined overhead rate, Terri divided her estimate of the total manufacturing overhead for the coming year by the production manager’s estimate of the total direct labor-hours for the coming year. She took her computations to the division’s general manager for approval but was quite surprised when he suggested a modification in the base. Her conversation with the general manager of the Home Security Systems Division, Harry Irving, went like this:

Ronsin: Here are my calculations for next year’s predetermined overhead rate. If you approve, we can enter the rate into the computer on January 1 and be up and running in the job-order costing system right away this year.

Irving:   Thanks for coming up with the calculations so quickly, and they look just fine. There is, how- ever, one slight modification I would like to see. Your estimate of the total direct labor-hours for the year is 440,000 hours. How about cutting that to about 420,000 hours?

Ronsin: I don’t know if I can do that. The production manager says she will need about 440,000 direct labor-hours to meet the sales projections for the year. Besides, there are going to be over 430,000 direct labor-hours during the current year and sales are projected to be higher next year.

Irving: Teri, I know all of that. I would still like to reduce the direct labor-hours in the base to some- thing like 420,000 hours. You probably don’t know that I had an agreement with your predecessor as divisional controller to shave 5% or so off the estimated direct labor-hours every year. That way, we kept a reserve that usually resulted in a big boost to net operating income at the end of the fiscal year in December. We called it our Christmas bonus. Corporate headquarters always seemed as pleased as punch that we could pull off such a miracle at the end of the year. This system has worked well for many years, and I don’t want to change it now.

Required:

Assume the following information:

Direct Materials

$40

per unit

Direct Labor

$20

per unit

Total Estimated Manufacturing Overhead

$8,400,000

Manufacturing overhead is allocated based on estimated direct-labor hours.

Each unit of product requires 1 direct labor hour.

Calculate the cost of one unit of product, assuming that the overhead per unit is based on Terri Ronson’s estimate of 440,000 hours. (Round all dollar figures to two decimal places.)

If 442,000 units were produced, how much overhead was applied to work in process.

Calculate the cost of one unit of product, assuming that the overhead per unit is based on her supervisors preferred estimate of 420,000 hours. (Round all dollar figures to two decimal places.)

If 442,000 units were produced, how much overhead was applied to work in process.

During the year, the company produced and sold 442,000 units, and incurred actual overhead of $8,450,000, what is the under/overapplied overhead if:

The estimated Direct Labor Hours is 440,000.

The estimated Direct Labor Hours is 420,000.

All over-applied and under-applied overhead applied directly to cost of goods sold. Assume that the company had $900,000 in net operating income before the over/under applied overhead adjustment is made. What is the revised net income after the over/underapplied overhead adjustment?

Should Terri Ronson go along with the general manager’s request to reduce the direct labor hours in the predetermined overhead rate computation to 420,000 hours? Be sure to discuss the operational and ethical issues related to this decision.

Deliverables:

Submit an Excel spreadsheet that documents the calculations made for steps 1-3 above. All items should be clearly labeled, and appropriate formulas should be used to perform your calculations.

For step 4, submit a 4-6 minute narrated PowerPoint (preferably using VoiceThread) that highlights your discussion of the operational and ethical issues that Teri is facing as a result of the request to reduce the direct labor hours. Be sure to make a recommendation in regard to making this decision. The presentation should be 3-4 slides.

Post your PowerPoint and workbook on behalf of your team to the Week 2 Assignments Page for the case study.

NOTE: as a team project, a team collaboration tool (such as Big Blue Button) should be used for the students to collaborate on the project!

Homework Answers

Answer #1
440000 DLH 420000 DLH
direct mat $40 $40
direct labor $20 20
Overhead applied (8400000/440000) = 19.09 (8400000/420000) = 20
Cost per unit $79.09 $80
Applied overhead to WIP 442000*19.09=$8437780 442000*20=$8840000
Actual overhead $84,50,000.00 $84,50,000.00
Under applied $12,220.00
Over applied $3,90,000.00
Before NOI $9,00,000.00 $9,00,000.00
After NOI $8,87,780.00 $12,90,000.00
By reducing the direct labor hours in the predetermined overhead rate computation to 442,000 hours, the general manager has been over-appling the overhead to the production. It would make the cost per unit high than the actual. At the end of the year, the over-applied overhead has to be reversed to some cost absorbent. It is ethically not correct because it raised the cost indicated by the produced output than that of actual cost incurred.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
CASE 3–18 Ethics and the Manager [Course Objective B] Terri Ronsin had recently been transferred to...
CASE 3–18 Ethics and the Manager [Course Objective B] Terri Ronsin had recently been transferred to the Home Security Systems Division of National Home Products. Shortly after taking over her new position as divisional controller, she was asked to develop the division’s predetermined overhead rate for the upcoming year. The accuracy of the rate is important because it is used throughout the year and any overapplied or underapplied over- head is closed out to Cost of Goods Sold at the...
Assume the following information: Direct Materials $40 per unit Direct Labor $20 per unit Total Estimated...
Assume the following information: Direct Materials $40 per unit Direct Labor $20 per unit Total Estimated Manufacturing Overhead $8,400,000 Manufacturing overhead is allocated based on estimated direct-labor hours. Each unit of product requires 1 direct labor hour. 1. Calculate the cost of one unit of product, assuming that the overhead per unit is based on Terri Ronson’s estimate of 440,000 hours. (Round all dollar figures to two decimal places.) a. If 442,000 units were produced, how much overhead was applied...
Melinda Baker had recently been transferred to the Home Security Division of ADP. Shortly after taking...
Melinda Baker had recently been transferred to the Home Security Division of ADP. Shortly after taking over her new position as controller, she was asked to develop the division’s predetermined overhead rate for the upcoming year. The accuracy of the rate is important because it is used all year long and any overapplied or under- applied overhead is closed out to Cost of Goods Sold at the end of the year. ADP uses direct labor-hours as the allocation base for...
Granite Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a...
Granite Company uses a job-order costing system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor-hours. Last year, manufacturing overhead and direct labor-hours were estimated at $80,000 and 16,000 hours respectively, for the year. In June, Job #315 was completed. Materials costs on the job totaled $1,500 and labor costs totaled $2,400 at $6 per hour. At the end of the year, it was determined that the company worked 15,000 direct labor-hours for...
E2-18 (Algo) Calculating Actual and Applied Manufacturing Overhead Costs and Over- or Underapplied Overhead Costs [LO...
E2-18 (Algo) Calculating Actual and Applied Manufacturing Overhead Costs and Over- or Underapplied Overhead Costs [LO 2-3, 2-4, 2-5, 2-6] Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $193,000. Estimated direct labor cost was $478,640 for 19,300 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct...
5. Assume (1) a company’s plantwide predetermined overhead rate is $13.00 per direct labor-hour, and (2)...
5. Assume (1) a company’s plantwide predetermined overhead rate is $13.00 per direct labor-hour, and (2) its job cost sheet for Job X shows that this job incurred direct materials and direct labor charges of $500 and $360, respectively. If Job X’s total job cost is $1,289, how many direct labor-hours were worked on this job? 6. Assume (1) actual machine-hours worked during the period of 54,000 hours, (2) estimated machine-hours to be worked during the period of 55,600 hours,...
At the beginning of the year, Learer Company’s manager estimated total direct labor cost assuming 40...
At the beginning of the year, Learer Company’s manager estimated total direct labor cost assuming 40 persons working an average of 3,000 hours each at an average wage rate of $20 per hour. The manager also estimated the following manufacturing overhead costs for the year. Indirect labor $ 316,200 Factory supervision 100,000 Rent on factory building 147,000 Factory utilities 95,000 Factory insurance expired 75,000 Depreciation—Factory equipment 521,000 Repairs expense—Factory equipment 67,000 Factory supplies used 75,800 Miscellaneous production costs 43,000 Total...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead...
ob-Order Costing Ace Custom Jewelry Company uses a job-order cost system. The company applies manufacturing overhead to jobs using a predetermined overhead rate based on direct labor hours. The estimated MOH was $135,000 for the year and the estimated direct labor hours were 15,000 hours. In May, Job #378 was completed. Direct materials totaled $8,500. Total labor costs were $14,000 at $16 per hour. At the end of the year, it was determined that the company worked 16,000 direct labor...
In December 2010, Gomez Company’s manager estimated next year’s total direct labor cost assuming 50 persons...
In December 2010, Gomez Company’s manager estimated next year’s total direct labor cost assuming 50 persons working an average of 2,060 hours each at an average wage rate of $15 per hour. The manager also estimated the following manufacturing overhead costs for year 2011.         Indirect labor $ 164,150   Factory supervision 127,000   Rent on factory building 89,000   Factory utilities 45,400   Factory insurance expired 35,400   Depreciation—Factory equipment 249,000   Repairs expense—Factory equipment 30,500   Factory supplies used 34,500   Miscellaneous production costs 13,000...
In December 2010, Gomez Company’s manager estimated next year’s total direct labor cost assuming 50 persons...
In December 2010, Gomez Company’s manager estimated next year’s total direct labor cost assuming 50 persons working an average of 2,020 hours each at an average wage rate of $15 per hour. The manager also estimated the following manufacturing overhead costs for year 2011.         Indirect labor $ 167,650   Factory supervision 123,000   Rent on factory building 76,000   Factory utilities 46,000   Factory insurance expired 35,100   Depreciation—Factory equipment 249,000   Repairs expense—Factory equipment 31,500   Factory supplies used 34,400   Miscellaneous production costs 10,000...