Basic List Price of Plant 240,000
Trade Discount 12.5% on list price.
Ancillary costs:
Shipping and Handling Cost 2,750
Pre-Production Testing 12500
Maintenance Cost 24000
Site Preparation Cost
Electrical Cable Installation 14000
Concrete Reinforcement 4500
Own Labour Cost 7500
Broadoak paid for the plant (excluding the ancillary costs} within four weeks of order, thereby obtaining an early settlement discount of 10%.
Broadoak had incorrectly Specified the Power loading of the original electrical cable to be installed by the contractor_ The cost of correcting this error of $6000 is included in the above figure of$14,000.The plant is expected to last for 10 years. At the end of tenth year there will be
compulsory costs of $15000 to dismantle the plant and $3,000 to restore the site to its original use condition_
Required: Calculate the amount at which the initial cast of the plant should be measured