Question

Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...

Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $60.00 per batch Movement 15.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 4.00 per inch Shaping 25.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 100 pounds each required the following: • Four batch moves • Two sets of inspections • Drilling ten holes in each unit • Completing 100 inches of welds on each unit • Forty-five minutes of shaping for each unit • One hour of assembly per unit Determine the activity cost of converting the raw materials into 50 fireplace inserts. Round answers to the nearest whole number, if applicable.

Homework Answers

Answer #1

STEP 1 - FIND rate per activity

activity cost cost driver cost of converting the raw materials into 50 fireplace inserts working
machine set up $60 per batch 1 batch 60$[$60*1batch]
Movement $15 per batch 4 batches moves 60$[$15*4]
$0.10 per pound 100 pounds 500$[$0.10*5000pounds] 100 pounds *50fireplaces
drilling $3 per hole 10 holes 1500$[500holes*3$ per hole] 10holes in each unit*50units
hole welding $4.00 per inch 100 inch 20000$[5000inches*$4] 100inch per unit*50units
shaping $25 per hour 45 minutes 938$[37.5hours *25 per hour] 45 minutes each unit *50units / 60minuts
assembly $18 per hour 1 hour 900$[50hours*18$] 1hour*50unit
inspection $2 per unit 2 inspections $200 [$2 per unit*50units*2 sets of inspection]
total cost 24158$
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $60.00 per batch Movement 15.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 4.00 per inch Shaping 25.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 100 pounds each required the following: • Four batch moves...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following...
Two-Stage ABC for Manufacturing: Reassigning Costs to Cost Objectives National Technology, LTD. has developed the following activity cost information for its manufacturing activities: Activity Activity Cost Machine setup $70.00 per batch Movement 20.00 per batch 0.10 per pound Drilling 3.00 per hole Welding 8.00 per inch Shaping 29.00 per hour Assembly 18.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts that weighed 150 pounds each required the following: • Three batch moves...
Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objectives Regal Products has developed the following...
Stage 2 ABC for Manufacturing: Reassigning Costs to Cost Objectives Regal Products has developed the following activity cost information for its manufacturing activities: Activity Activity cost Machine setup $60.00 per batch Movement 15.00 per batch move 0.10 per pound Drilling 5.00 per hole Welding 2.00 per inch Shaping 25.00 per hour Assembly 19.00 per hour Inspection 2.00 per unit Filling an order for a batch of 50 fireplace inserts (each insert weighing 150 pounds) required the following: Three batch moves...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information...
Two-Stage ABC for Manufacturing with Variances Montreat Manufacturing has developed the following activity cost pool information for its 2016 manufacturing activities: Budgeted Activity Cost Activity Cost Driver at Practical Capacity Purchasing and materials handling $675,000 900,000 kilograms Setup 700,000 1,120 setups Machine operations 954,000 12,000 hours First unit inspection 50,000 1,000 batches Packaging 250,000 312,500 units Actual 2016 production information is as follows: Standard Product A Standard Product B Specialty Products Units 150,000 100,000 50,000 Batches 100 80 600 Setups*...
Drilling Company uses activity-based costing and provides this information: Manufacturing Activity Cost Driver Driver Rate Materials...
Drilling Company uses activity-based costing and provides this information: Manufacturing Activity Cost Driver Driver Rate Materials handling Number of parts $ 0.60 Machinery Number of machine hours 51.00 Assembly Number of parts 2.85 Inspection Number of finished units 30.00 Drilling has just completed 80 units of a component for a customer. Each unit required 100 parts and 3 machine hours. The prime cost is $1,300 per finished unit. All other manufacturing costs are classified as manufacturing overhead. Required: 1. Compute...
Activity-Based Budget Highlands Industries has the following budget information available for February: Units manufactured 25,000 Factory...
Activity-Based Budget Highlands Industries has the following budget information available for February: Units manufactured 25,000 Factory administration $145,000 Assembly 0.25 hour per unit X $20 Direct materials 3 pounds per unit X $6 Inspection $40 per batch of 1,000 units Manufacturing overhead $8 per unit Product development $50,000 Setup cost $100 per batch of 1,000 units Use activity-based costing to prepare a manufacturing cost budget for February. Clearly distinguish between unit, batch, and facility-level costs. HighlandsIndustries Activity-Based Manufacturing Cost Budget...
Reducir, Inc., produces two different types of hydraulic cylinders. Reducir produces a major subassembly for the...
Reducir, Inc., produces two different types of hydraulic cylinders. Reducir produces a major subassembly for the cylinders in the Cutting and Welding Department. Other parts and the subassembly are then assembled in the Assembly Department. The activities, expected costs, and drivers associated with these two manufacturing processes are given below. Process Activity Cost Activity Driver Expected Quantity Cutting and Welding Welding $ 776,000    Welding hours 4,000 Machining 450,000    Machine hours 10,000 Inspecting 448,250    No. of inspections 1,000 Materials handling 300,000...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $344,760 Machine hours Assembly 231,200 Direct labor hours Inspecting 38,080 Number of inspections Setup 33,360 Number of setups Materials handling 43,680 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $250,900 Machine hours Assembly 154,000 Direct labor hours Inspecting 26,620 Number of inspections Setup 43,120 Number of setups Materials handling 45,120 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the...
Lonsdale Inc. manufactures entry and dining room lighting fixtures. Five activities are used in manufacturing the fixtures. These activities and their associated budgeted activity costs and activity bases are as follows: Activity Budgeted Activity Cost Activity Base Casting $325,710 Machine hours Assembly 202,500 Direct labor hours Inspecting 33,150 Number of inspections Setup 36,480 Number of setups Materials handling 42,750 Number of loads Corporate records were obtained to estimate the amount of activity to be used by the two products. The...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT