Budgeting Production and Purchases and Just-In-Time Materials Inventory Hancock Manufacturing, Inc. is preparing budgets for the...

Budgeting Production and Purchases and Just-In-Time Materials Inventory
Hancock Manufacturing, Inc. is preparing budgets for the third quarter of 2016. Hancock produces only one product in its factory. This product requires 5 pounds of material B, 2 pounds of material G, and a component, K, that is purchased from another manufacturer. Hancock operates on a just-in-time basis for material B. As a result, Hancock maintains no inventory of material B. On July 1, 2016, the inventory of material G is expected to be 3,000 pounds and the inventory of component K is expected to be 1,500 units. Hancock wants the inventories of G and K at September 30, 2016, to be 20% less than the inventories at July 1, 2016. The inventory of finished products at June 30, 2016, is expected to be 2,000 units; the desired inventory at September 30, 2016, is 4,000 units to allow a buildup for heavy sales in the fourth quarter. The sales forecast for the third quarter is 13,000 units at $300 each. Budgeted purchase costs are $10 per pound for B, $7 per pound for G, and $40 per component for K.

Do not use negative signs with any of your answers below.

a. Prepare the production budget for Hancock Manufacturing, Inc., for the third quarter of 2016.

Hancock Manufacturing, Inc.
Production Budget
For the Quarter Ended September 30, 2016
Forecast unit sales Answer
Desired ending inventory Answer
Quantity to be available Answer
Beginning inventory Answer
Total production to be scheduled Answer

b. Prepare the direct material budget for Hancock Manufacturing, Inc., for the third quarter of 2016.

Hancock Manufacturing, Inc.
Direct Material Budget
For the Quarter Ended September 30, 2016
Material B Material G Component K
Scheduled production Answer Answer Answer
X Answer X Answer X Answer
Direct material required Answer Answer Answer
Desired ending inventories Answer Answer Answer
Total to be available Answer Answer Answer
Beginning inventory Answer Answer Answer
Total units of material to be purchased Answer Answer Answer
Unit purchase price X $Answer X $Answer X $Answer
Total material purchases $Answer $Answer $Answer

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 15,700 26,800 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit 1.50 lb. per unit Tomato...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 16,500 25,400 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit 1.50 lb. per unit Tomato...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its A budget of estimated...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its A budget of estimated unit production.production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 16,600 20,900 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 15,800 22,000 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit 1.50 lb. per unit Tomato...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 15,500 23,800 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit 1.50 lb. per unit Tomato...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 15,500 23,800 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit 1.50 lb. per unit Tomato...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 13,300 20,700 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit 1.50 lb. per unit Tomato...
Required information Problem 20-1A Manufacturing: Preparing production and manufacturing budgets LO C2, P1 [The following information...
Required information Problem 20-1A Manufacturing: Preparing production and manufacturing budgets LO C2, P1 [The following information applies to the questions displayed below.] Black Diamond Company produces snow skis. Each ski requires 2 pounds of carbon fiber. The company’s management predicts that 5,000 skis and 6,000 pounds of carbon fiber will be in inventory on June 30 of the current year and that 150,000 skis will be sold during the next (third) quarter. A set of two skis sells for $300....
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following...
Direct Materials Purchases Budget Lorenzo’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for September: Units 12" Pizza 16" Pizza Budgeted production volume 13,200 23,300 Three direct materials are used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows: 12" Pizza 16" Pizza Direct materials: Dough 0.80 lb. per unit 1.50 lb. per unit Tomato...
Problem 20-1A Manufacturing: Preparing production and manufacturing budgets LO C2, P1 [The following information applies to...
Problem 20-1A Manufacturing: Preparing production and manufacturing budgets LO C2, P1 [The following information applies to the questions displayed below.] Black Diamond Company produces snow skis. Each ski requires 2 pounds of carbon fiber. The company’s management predicts that 5,000 skis and 6,000 pounds of carbon fiber will be in inventory on June 30 of the current year and that 150,000 skis will be sold during the next (third) quarter. A set of two skis sells for $300. Management wants...