Question

The Lee Corporation uses a job-order costing system. The following data were recorded for June: June...

The Lee Corporation uses a job-order costing system. The following data were recorded for June:

June 1 Added During June
Job Number Work in Process Inventory Direct Materials Direct Labor
235 $2,600 $640 $430
236 $1,600 $860 $1,070
237 $1,090 $1,280 $1,870
238 $850 $1,640 $2,410


Overhead is charged to production at 65% of direct materials cost. Jobs 235, 237, and 238 were completed during June and transferred to finished goods. Jobs 235 and 238 have been delivered to customers. Actual manufacturing overhead was equal to manufacturing overhead applied. There were no Finished Goods inventories at the beginning of June.

Lee's Work in Process inventory balance on June 30 was:

rev: 10_24_2017_QC_CS-103206

A) $4,089

B) $4,249

C) $9,599

D) $3,530

Homework Answers

Answer #1

Ans- Computing the balance work in Process inventory balance on June 30:

Job: 236

Particulars Amount ($)
Beginning work in process inventory 1,600
Add:
Direct material 860
Direct labor 1,070
Overhead ($860*65%) 559
Ending work in process inventory $4,089

Hence, the work in process inventory on 30th June is $4,089, Therefore the correct option is A-$4,089

Note-

The completed jobs will not form part of the closing work in process inventory. Therefore only Job no.236 forms part of the ending work in process inventory.

Kindly give thumbsup if u like my answer....Thanks!!!

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current year. The predetermined overhead rate is 30% of direct labor costs. The following cost information is available (all materials and time ticket information apply to direct costs): Job Material Requisitions Time Tickets 101 $91,000 $36,000 102 $67,000 $62,300 103 $47,000 $55,500 104 $35,700 $42,000 105 $39,000 $92,750 Part 1—Complete the job cost sheets for each job. Job No. 101 Job No. 102 Job No....
The Milo Max Company uses a job-order cost system. The following data were recorded for October:...
The Milo Max Company uses a job-order cost system. The following data were recorded for October: - Job Number October 1 Work-in-Process Direct Materials Direct Labor MM002…………. $4,550 $780 $520 MM003…………. 0 $1,100 $1,300 MM004…………. $13,400 $1,560 $2,270 MM005…………. $ 1,040 $2,000 $2,920 Overhead is charged to production at 110% of direct labor cost. Jobs MM002, MM003 and MM005 were completed during October and transferred to finished goods. Jobs MM002 and MM003 have been delivered to customers. Required:- What was...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 16,500 $ 9,300 $ 0...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...
Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 19,500 $ 12,300 $ 0...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 40,000 Work in process $ 18,000 Finished goods $ 35,000 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $16.25 per direct labor-hour was based on a cost formula that estimated $650,000 of total manufacturing overhead for an estimated activity level of 40,000 direct...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances...
Bunnell Corporation is a manufacturer that uses job-order costing. On January 1, the company’s inventory balances were as follows: Raw materials $ 50,000 Work in process $ 30,800 Finished goods $ 43,200 The company applies overhead cost to jobs on the basis of direct labor-hours. For the current year, the company’s predetermined overhead rate of $12.00 per direct labor-hour was based on a cost formula that estimated $480,000 of total manufacturing overhead for an estimated activity level of 40,000 direct...
Hildreth Company uses a job order cost system. The following data summarize the operations related to...
Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $2,120. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $1,820 $2,040 102 2,220 2,750 103 1,470 1,350 104 4,990 5,060 105 3,170 3,860 106 2,310 2,450 For general factory use 620 3,020 Factory overhead costs incurred on account, $3,480. Depreciation of machinery and equipment, $1,450. The factory overhead...
J Company has the following information for the year related to its job order costing system....
J Company has the following information for the year related to its job order costing system. Work-In Process - Beginning Inventory $ 18,000 Finished Goods - Beginning Inventory 12,000 Direct materials placed in production 80,000 Direct labor incurred 190,000 Actual manufacturing overhead incurred 300,000 Manufacturing overhead applied to production 295,000 Cost of jobs completed and transferred 500,000 The cost of J Company's ending inventory of Work in Process is:
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide...
Br3-Pf Company uses a job-order costing system and applies overhead costs to jobs using a plant-wide rate of 90% of direct materials cost. Br3-Pf Company began work on four jobs during June. Information related to the four jobs appears below: Job #1 Job #2 COSTS ADDED DURING JUNE direct materials .............. $5,800 $7,500 direct labor .................. $7,300 $6,300 Job #3 Job #4 COSTS ADDED DURING JUNE direct materials .............. $8,200 $6,400 direct labor .................. $7,920 $7,560 By the end of...
7) Brand Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based...
7) Brand Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on total fixed manufacturing overhead cost of $225,700, variable manufacturing overhead of $3.00 per machine-hour, and 37,000 machine-hours. The company has provided the following data concerning Job A424 which was recently completed: Number of units in the job 20 Total machine-hours 80 Direct materials $ 910 Direct labor cost $ 1,820...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT