Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates:
Machining | Finishing | Total | ||||
Estimated total machine-hours (MHs) | 3,000 | 7,000 | 10,000 | |||
Estimated total fixed manufacturing overhead cost | $ | 8,400 | $ | 53,200 | $ | 61,600 |
Estimated variable manufacturing overhead cost per MH | $ | 2.00 | $ | 2.00 | ||
During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data concerning those two jobs follow:
Job B | Job K | |||||
Direct materials | $ | 21,600 | $ | 9,000 | ||
Direct labor cost | $ | 22,100 | $ | 8,500 | ||
Machining machine-hours | 2,500 | 500 | ||||
Finishing machine-hours | 2,000 | 5,000 | ||||
Required:
a. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate that overhead rate. (Round your answer to 2 decimal places.)
b. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job B. (Do not round intermediate calculations.)
c. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job K. (Do not round intermediate calculations. Round your answer to the nearest whole dollar amount.)
d. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments. What is the departmental predetermined overhead rate in the Machining department? (Round your answer to 2 decimal places.)
e. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. What is the departmental predetermined overhead rate in the Finishing department? (Round your answer to 2 decimal places.)
f. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job B? (Do not round intermediate calculations.)
g. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job K? (Do not round intermediate calculations.)
a) Plantwide overhead rate = (10000*2+61600)/10000 = 8.16 per MH
b) Manufacturing overhead applied for Job B = 4500*8.16 = 36720
c)Manufacturing overhead applied for Job K = 5500*8.16 = 44880
d) Departmental overhead rate for Machining = 8400/3000+2 = 4.8 per MH
e) Finishing overhead rate = 53200/7000+2 = 9.6 per MH
f) Manufacturing overhead applied to Job B = (2500*4.8+2000*9.6) = 31200
g) Manufacturing overhead applied to Job K = (500*4.8+5000*9.6) = 50400