Question

Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the...

Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates:

Machining Finishing Total
Estimated total machine-hours (MHs) 3,000 7,000 10,000
Estimated total fixed manufacturing overhead cost $ 8,400 $ 53,200 $ 61,600
Estimated variable manufacturing overhead cost per MH $ 2.00 $ 2.00

During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data concerning those two jobs follow:

Job B Job K
Direct materials $ 21,600 $ 9,000
Direct labor cost $ 22,100 $ 8,500
Machining machine-hours 2,500 500
Finishing machine-hours 2,000 5,000

Required:

a. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate that overhead rate. (Round your answer to 2 decimal places.)

b. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job B. (Do not round intermediate calculations.)

c. Assume that the company uses a plantwide predetermined manufacturing overhead rate based on machine-hours. Calculate the amount of manufacturing overhead applied to Job K. (Do not round intermediate calculations. Round your answer to the nearest whole dollar amount.)

d. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both departments. What is the departmental predetermined overhead rate in the Machining department? (Round your answer to 2 decimal places.)

e. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. What is the departmental predetermined overhead rate in the Finishing department? (Round your answer to 2 decimal places.)

f. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job B? (Do not round intermediate calculations.)

g. Assume that the company uses departmental predetermined overhead rates with machine-hours as the allocation base in both production departments. How much manufacturing overhead will be applied to Job K? (Do not round intermediate calculations.)

Homework Answers

Answer #1

a) Plantwide overhead rate = (10000*2+61600)/10000 = 8.16 per MH

b) Manufacturing overhead applied for Job B = 4500*8.16 = 36720

c)Manufacturing overhead applied for Job K = 5500*8.16 = 44880

d) Departmental overhead rate for Machining = 8400/3000+2 = 4.8 per MH

e) Finishing overhead rate = 53200/7000+2 = 9.6 per MH

f) Manufacturing overhead applied to Job B = (2500*4.8+2000*9.6) = 31200

g) Manufacturing overhead applied to Job K = (500*4.8+5000*9.6) = 50400

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the...
Bierce Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 6,000 4,000 10,000 Estimated total fixed manufacturing overhead cost $ 10,200 $ 24,400 $ 34,600 Estimated variable manufacturing overhead cost per MH $ 2.30 $ 4.00 During the most recent month, the company started and completed two jobs--Job B and Job K. There were no beginning inventories. Data...
Spencer Corporation has two manufacturing departments--Forming and Customizing. The company used the following data at the...
Spencer Corporation has two manufacturing departments--Forming and Customizing. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Forming Customizing Total Estimated total machine-hours (MHs) 6,000 4,000 10,000 Estimated total fixed manufacturing overhead cost $ 12,600 $ 10,800 $ 23,400 Estimated variable manufacturing overhead cost per MH $ 2.50 $ 5.00 During the period, the company started and completed two jobs--Job C and Job L. Data concerning those two jobs follow: Job C...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the...
Harnett Corporation has two manufacturing departments--Molding and Assembly. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Molding Assembly Total Estimated total machine-hours (MHs) 3,000 7,000 10,000 Estimated total fixed manufacturing overhead cost $ 12,000 $ 39,200 $ 51,200 Estimated variable manufacturing overhead cost per MH $ 1.00 $ 2.00 During the period, the company started and completed two jobs--Job E and Job M. Data concerning those two jobs follow: Job E...
Sanderlin Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the...
Sanderlin Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 5,000 5,000 10,000 Estimated total fixed manufacturing overhead cost $ 26,500 $ 13,500 $ 40,000 Estimated variable manufacturing overhead cost per MH $ 2.00 $ 3.00 During the most recent month, the company started and completed two jobs--Job C and Job L. There were no beginning inventories. Data...
Sanderlin Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the...
Sanderlin Corporation has two manufacturing departments--Machining and Finishing. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Finishing Total Estimated total machine-hours (MHs) 5,000 5,000 10,000 Estimated total fixed manufacturing overhead cost $ 26,500 $ 13,500 $ 40,000 Estimated variable manufacturing overhead cost per MH $ 2.00 $ 3.00 During the most recent month, the company started and completed two jobs--Job C and Job L. There were no beginning inventories. Data...
Hultquist Corporation has two manufacturing departments--Forming and Customizing. The company used the following data at the...
Hultquist Corporation has two manufacturing departments--Forming and Customizing. The company used the following data at the beginning of the period to calculate predetermined overhead rates: Forming Customizing Total Estimated total machine-hours (MHs) 6,000 4,000 10,000 Estimated total fixed manufacturing overhead cost $ 24,000 $ 10,400 $ 34,400 Estimated variable manufacturing overhead cost per MH $ 1.00 $ 2.00 During the period, the company started and completed two jobs--Job C and Job L. Data concerning those two jobs follow: Job C...
Morataya Corporation has two manufacturing departments--Machining and Assembly. The company used the following data at the...
Morataya Corporation has two manufacturing departments--Machining and Assembly. The company used the following data at the beginning of the year to calculate predetermined overhead rates: Machining Assembly Total Estimated total machine-hours (MHs) 7,000 3,000 10,000 Estimated total fixed manufacturing overhead cost $ 39,200 $ 6,600 $ 45,800 Estimated variable manufacturing overhead cost per MH $ 1.90 $ 2.10 During the most recent month, the company started and completed two jobs--Job B and Job G. There were no beginning inventories. Data...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 7,056,000 $ 441,000 $ 7,497,000 Direct labor-hours 21,000 336,000 357,000 Machine-hours 336,000 16,000 352,000 Job A Machining Assembly Total Direct labor-hours 5 10 15 Machine-hours 11 2...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 9,522,000 $ 529,000 $ 10,051,000 Direct labor hours 23,000 414,000 437,000 Machine hours 414,000 18,000 432,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead...
Mason Company has two manufacturing departments—Machining and Assembly. The company considers all of its manufacturing overhead costs to be fixed costs. It provided the following estimates at the beginning of the year as well as the following information with respect to Jobs A and B: Estimated Data Machining Assembly Total Manufacturing overhead $ 18,032,000 $ 784,000 $ 18,816,000 Direct labor hours 28,000 644,000 672,000 Machine hours 644,000 23,000 667,000 Job A Machining Assembly Total Direct labor hours 5 10 15...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT