Wolfpack Company uses job-order costing. At the end of the month, the following data was gathered:
Job # |
Total Cost |
Complete? |
Sold? |
803 |
$611 |
yes |
yes |
804 |
423 |
yes |
no |
805 |
805 |
no |
no |
806 |
682 |
yes |
yes |
807 |
525 |
yes |
no |
808 |
250 |
no |
no |
809 |
440 |
yes |
yes |
810 |
773 |
yes |
no |
811 |
267 |
no |
no |
812 |
341 |
no |
no |
Wolfpack’s selling price is cost plus 50% for each of its jobs.
What is the selling price of Job 806?
Select one:
a. $682
b. $1,320
c. $1,023
d. $1,440
e. $920
QUESTION 2:
Which of the following statements about a capital investment project’s internal rate of return is true?
Select one:
a. The internal rate of return is the minimum required rate of return for a project.
b. The internal rate of return indicates the number of years it takes the project’s cash inflows to equal or exceed the project’s cost.
c. The internal rate of return is the actual rate of return of the capital investment project.
d. The internal rate of return is the maximum required rate of return for a project.
QUESTION 3
Raleigh Clothes Ltd. uses job order costing to measure and track product costs. Raleigh has determined that machine hours drive its manufacturing overhead costs. During the month of June, the following data were available for Product #95:
Direct labor 350 hours at $10 per hour
Direct materials 40 square yards at $25 per yard
Machine hours used 1,000 hours
If total manufacturing overhead costs during the month totaled $100,000 when a total of 25,000 machine hours were used, what will be the total manufacturing cost of Product #95?
Select one:
a. $ 3,500
b. $ 4,500
c. $12,500
d. $ 4,000
e. $ 8,500
1)
Given cost of job 806 = $682
Selling price is cost plus 50%
Therefore selling price of job 806 = 682 + 341(i.e.682*50%) = $1,023
Answer: C
2)
Internal rate of return is the rate of return on an investment. It is the rate of return at which discounted cash inflows from a project equals the initial investment. It is the minimum return to be earned on investment. The project should be accepted only if actual rate of return is more than IRR
Answer: A
3)
Total manufacturing overhead cost = $100,000
Total machine hours = 25,000
Therefore Manufacturing overhead per machine hour = 100,000/25,000 = $4 per machine hout
Particulars | Amount $ |
---|---|
Direct labor (350 hours * $10) | 3,500 |
Direct material (40*25) | 1,000 |
Manufacturing overhead costs (1000 hours * $4 per hour) | 4,000 |
Total manufacturing cost | 8,500 |
Answer: e
Get Answers For Free
Most questions answered within 1 hours.