What are the three Cost Drivers for the following two activities:
1). Materials Purchased.
2). Customer Service.
Please explain your answer.
Cost drivers are activity units which helps to assign the cost to various activities in the organisation.
1) Material Purchased : for Material purchases, there is primarility only one cost driver i.e. No of Purchase orders created
2) Customer Service : : For customer service cost drivers can be No of service calls attended, No of Hours spent for servicing, No Service staff in service department etc.
-------------------------------------------------------------------------
If you have any queries kindly drop a comment.