Question

Hildreth Company uses a job order cost system. The following data summarize the operations related to...

Hildreth Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations:

  1. Materials purchased on account, $2,120.
  2. Materials requisitioned and factory labor used:
    Job No. Materials Factory Labor
    101 $1,820 $2,040
    102 2,220 2,750
    103 1,470 1,350
    104 4,990 5,060
    105 3,170 3,860
    106 2,310 2,450
    For general factory use 620 3,020
  3. Factory overhead costs incurred on account, $3,480.
  4. Depreciation of machinery and equipment, $1,450.
  5. The factory overhead rate is $35 per machine hour. Machine hours used:
    Job No. Machine Hours
    101 37
    102 44
    103 18
    104 67
    105 37
    106 32
    Total 235
  6. Jobs completed: 101, 102, 103, and 105.
  7. Jobs were shipped and customers were billed as follows: Job 101, $6,190; Job 102, $7,810; Job 105, $10,010.

Required:

1. Journalize the entries to record the summarized operations. For a compound transaction, if an amount box does not require an entry, leave it blank.

Entries Description Debit Credit
a. Materials
Accounts Payable
b. Work in Process
Factory Overhead
Materials
Wages Payable
c. Factory Overhead
Accounts Payable
d. Factory Overhead
Accumulated Depreciation-Machinery and Equipment
e. Work in Process
Factory Overhead
f. Finished Goods
Work in Process
g. Sale Accounts Receivable
Sales
g. Cost Cost of Goods Sold
Finished Goods

2. Post the appropriate entries to T accounts for Work in Process and Finished Goods, using the identifying letters as transaction codes. Insert memo account balances as of the end of the month.

Work in Process
(b) (f)
(e)
Bal.


Finished Goods
(f) (g)
Bal.

3. Prepare a schedule of unfinished jobs to support the balance in the work in process account.

Hildreth Company
Schedule of Unfinished Jobs
Job Direct Materials Direct Labor Factory Overhead Total
No. 104 $ $ $ $
No. 106
Balance of Work in Process, April 30 $

4. Prepare a schedule of completed jobs on hand to support the balance in the finished goods account.

Hildreth Company
Schedule of Completed Jobs
Job Direct Materials Direct Labor Factory Overhead Total
Finished Goods, April 30 (Job 103) $ $ $ $

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost...
Entries and Schedules for Unfinished Jobs and Completed Jobs Mellow Company uses a job order cost system. The following data summarize the operations related to production for April, the first month of operations: Materials purchased on account, $3,170. Materials requisitioned and factory labor used: Job No. Materials Factory Labor 101 $3,030 $3,160 102 3,700 4,270 103 2,450 2,090 104 8,300 7,840 105 5,270 5,970 106 3,850 3,790 For general factory use 1,030 4,680 Factory overhead costs incurred on account, $5,790....
Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related...
Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations: a. Materials purchased on account, $29,800. b. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $ 2,960 $2,775 302 3,620 3,750 303 2,400 1,875 304 8,100 6,860 305 5,100 5,250 306 3,750 3,340 For general factory use 1,080 4,100 c. Factory overhead costs incurred on account, $5,500. d. Depreciation of machinery and...
Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related...
Tybee Industries Inc. uses a job order cost system. The following data summarize the operations related to production for January, the first month of operations: a. Materials purchased on account, $29,800. b. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $ 2,960 $2,775 302 3,620 3,750 303 2,400 1,875 304 8,100 6,860 305 5,100 5,250 306 3,750 3,340 For general factory use 1,080 4,100 c. Factory overhead costs incurred on account, $5,500. d. Depreciation of machinery and...
Kurtz Fencing Inc. uses a job order cost system. The following data summarize the operations related...
Kurtz Fencing Inc. uses a job order cost system. The following data summarize the operations related to production for March, the first month of operations: a. Materials purchased on account, $30,100. b. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $3,110 $2,720 302 3,710 3,810 303 2,400 1,970 304 8,500 6,870 305 5,210 5,410 306 3,850 3,290 For general factory use 1,080 4,120 c. Factory overhead costs incurred on account, $5,440. d. Depreciation of machinery and equipment,...
Kurtz Fencing Inc. uses a job order cost system. The following data summarize the operations related...
Kurtz Fencing Inc. uses a job order cost system. The following data summarize the operations related to production for March, the first month of operations: a. Materials purchased on account, $31,030. b. Materials requisitioned and factory labor used: Job Materials Factory Labor 301 $3,060 $2,710 302 3,640 3,820 303 2,430 1,870 304 8,280 7,010 305 5,340 5,100 306 3,790 3,170 For general factory use 1,060 4,260 c. Factory overhead costs incurred on account, $5,290. d. Depreciation of machinery and equipment,...
Tybee Industries Inc. uses a job order cost system A type of cost accounting system that...
Tybee Industries Inc. uses a job order cost system A type of cost accounting system that provides for a separate record of the cost of each particular quantity of product that passes through the factory. . The following data summarize the operations related to production for January, the first month of operations: a. Materials purchased on account, $28,790. b. Materials requisitioned The form or electronic transmission used by a manufacturing department to authorize materials issuances from the storeroom. and factory...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current year. The predetermined overhead rate is 30% of direct labor costs. The following cost information is available (all materials and time ticket information apply to direct costs): Job Material Requisitions Time Tickets 101 $91,000 $36,000 102 $67,000 $62,300 103 $47,000 $55,500 104 $35,700 $42,000 105 $39,000 $92,750 Part 1—Complete the job cost sheets for each job. Job No. 101 Job No. 102 Job No....
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing...
The information below was taken from the job cost sheets of Bates Company. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 4,100 102 3,200 103 920 $ 2,000 104 2,100 4,500 105 5,700 106 3,800 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis...
Jenkins Company uses a job order cost system with overhead applied to jobs on the basis of direct labor hours. The direct labor rate is $20 per hour, and the predetermined overhead rate is $15 per direct labor hour. The company worked on three jobs during April. Jobs A and B were in process at the beginning of April. Job A was completed and delivered to the customer. Job B was completed during April, but not sold. Job C was...
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing...
The information below was taken from the job cost sheets of Igmund Manufacturing. Job Number Manufacturing Costs as of June 30 Manufacturing Costs in July 101 $ 6,600 102 5,280 103 960 $ 3,600 104 4,080 7,200 105 8,400 106 2,900 During July, jobs no. 103 and 104 were completed, and jobs no. 101, 102, and 104 were delivered to customers. Jobs no. 105 and 106 are still in process at July 31. a. Compute the work in process inventory...