Question

ABC Manufacturing Inc. ends the month with two jobs still in progress. Job 5 has​ $10,000...

ABC Manufacturing Inc. ends the month with two jobs still in progress. Job 5 has​ $10,000 of​ materials, $2,000 of direct labor and​ $8,000 of manufacturing overhead allocated. Job 6 was​ $30,000 of​ materials, $2,000 of direct labor and​ $10,000 of manufacturing overhead allocated. The cost of goods sold for the month was​ $40,000 and of that​ 30% was overhead. There were no finished goods in stock as the month ends. If the manufacturing overhead is underallocated by​ $10,000, which of the following choices would be the correct way to prorate​ it, assuming the proration is based on the allocated overhead in the ending balances of​ work-in-process, finished​ goods, and cost of goods​ sold? (Round any allocation percentages to one decimal​ place, X.X%.)

A.

Cost of goods sold should be increased by​ $4,000

B.

Job 5 should be allocated another​ $6,000 of cost

C.

Cost of goods sold should be reduced by​ $4,000

D.

Job 6 should be allocated another​ $6,000 of cost

Homework Answers

Answer #1
OH applied % of total Under-applied Oh Allocation of Under-applied Oh
Work in process Job 5 8000 26.67% 10000 2667
Work in process Job 6 10000 33.33% 10000 3333
Cost of goods sold 12000 40.00% 10000 4000
Total 30000 100.00% 10000
The Above allocated amount will increase the Cost of goods sold balance by $4,000, WIP Job 5 balance by $2667 and WIP Job 6 balance by $3333.
Answer is A. Cost of goods sold should be increased by $ 4,000
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct...
ABC Manufacturing uses normal costing and allocates manufacturing overhead to jobs based on a budgeted direct labor-hour rate for the actual direct labor hours. Any overallocated or underallocated overhead is written-off to the cost of goods sold at the end of the month. During April 2019, ABC Manufacturing recorded the following: Budgeted manufacturing overhead costs: $400,000 Budgeted direct labor-hours: 20,000 DLHRS Budgeted machine hours: 16,000 MHRS Actual manufacturing overhead costs: $360,000 Actual direct labor-hours:   22,500 DLHRS Actual machine hours: 15,000...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q.
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...
For its first month of operations, Stellar Company worked on only two jobs--Job X and Job...
For its first month of operations, Stellar Company worked on only two jobs--Job X and Job Y. Job X consisted of 500 units, 400 of which were sold to customers and 100 of which remained in Finished Goods at the end of the month. Job Y consisted of 200 units and it was incomplete at the end of the month. The company also provides the following data: Predetermined overhead rate (POHR) Actual direct labor hours (DLHs) used in each job:...
Reith Inc. has provided the following data for the month of November. There were no beginning...
Reith Inc. has provided the following data for the month of November. There were no beginning inventories; consequently, the direct materials, direct labor, and manufacturing overhead applied listed below are all for the current month. Work In Process Finished Goods Cost of Goods Sold Total Direct materials $ 1,850 $ 10,440 $ 58,560 $ 70,850 Direct labor 3,510 22,620 126,880 153,010 Manufacturing overhead applied 1,560 7,800 42,640 52,000 Total $ 6,920 $ 40,860 $ 228,080 $ 275,860 Manufacturing overhead for...
The following information is available for completed Job No. 404: Direct materials, $60,000; direct labor, $80,000;...
The following information is available for completed Job No. 404: Direct materials, $60,000; direct labor, $80,000; indirect labor, $10,000; manufacturing overhead, $120,000; units produced, 6,000; units sold, 5,000. Based on this information, the cost of finished goods on hand for this job is closest to
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current...
Dynamo Corporation uses a job order costing system. Five jobs were worked on during the current year. The predetermined overhead rate is 30% of direct labor costs. The following cost information is available (all materials and time ticket information apply to direct costs): Job Material Requisitions Time Tickets 101 $91,000 $36,000 102 $67,000 $62,300 103 $47,000 $55,500 104 $35,700 $42,000 105 $39,000 $92,750 Part 1—Complete the job cost sheets for each job. Job No. 101 Job No. 102 Job No....
[The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress...
[The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a...
Castagnola Inc. has provided the following data for the month of January. There were no beginning...
Castagnola Inc. has provided the following data for the month of January. There were no beginning inventories; consequently, the direct materials, direct labor, and manufacturing overhead applied listed below are all for the current month. Work In Process Finished Goods Cost of Goods Sold Total Direct materials $ 880 $ 5,500 $ 23,100 $ 29,480 Direct labor 4,100 17,600 73,920 95,620 Manufacturing overhead applied 2,460 7,380 31,160 41,000 Total $ 7,440 $ 30,480 $ 128,180 $ 166,100 Manufacturing overhead for...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories....
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. It started only two jobs during March—Job P and Job Q. Job P was completed and sold by the end of March and Job Q was incomplete at the end of March. The company uses a plantwide predetermined overhead rate based on direct labor-hours. The following additional information is available for the company as a whole and for Jobs P and Q (all data...