Ripley, Inc., costs products using a normal costing system. The following data are available for last year:
Budgeted: | ||
Overhead | $343,000 | |
Machine hours | 88,000 | |
Direct labor hours | 9,800 | |
Actual: | ||
Overhead | $342,200 | |
Machine hours | 85,800 | |
Direct labor hours | 9,580 | |
Prime cost | $1,464,700 | |
Number of units | 180,000 |
Overhead is applied on the basis of direct labor hours.
Required:
1. What was the predetermined overhead
rate?
$fill in the blank 1 per direct labor hour
2. What was the applied overhead for last
year?
$fill in the blank 2
3. Was overhead over- or underapplied, and by
how much?
= $fill in the blank 4
4. What was the total cost per unit produced?
(Carry your answer to four significant digits.)
$fill in the blank 5 per unit