Question

How would a very large Favourable Fixed Overhead Flexible Budget variance cause an unfavourable Labour Efficiency...

How would a very large Favourable Fixed Overhead Flexible Budget variance cause an unfavourable Labour Efficiency Variance and a unfavourable Material Efficiency Variance

Homework Answers

Answer #1

A favorable variance occurs when the cost to produce something is less than the budgeted cost. It means a business is making more profit than originally anticipated. Favorable variances could be the result of increased efficiencies in manufacturing, cheaper material costs, or increased sales.

Faverable Fixed Overhead Budget variances Could caused by spending the in excuss than budget and changes in the production volume.

Causes of Labour Unfaverable efficency variances:

  • Poor Supervision and workforce
  • Workforces mixes can have an impact upon Labour efficency levals
  • Resources shortages causing an unexpected delay and lowering of labour efficency levals

Causes of an unfaverable Material efficency Variances:

  • poor Inspection
  • changes in the production/design
  • careless way of handeling material by production department.
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,600 units. Manufacturing overhead is budgeted at $120,400 for the period (20% of this cost is fixed). The 16,730 hours worked during the period resulted in the production of 8,190 units. The variable manufacturing overhead cost incurred was $98,300 and the fixed manufacturing overhead cost was $28,100. 1.Calculate the variable overhead...
The calculation of direct labour variances shows a favourable labour rate variance of​ £5,000 and an...
The calculation of direct labour variances shows a favourable labour rate variance of​ £5,000 and an unfavourable labour efficiency variance of​ £5,000. Which of the following is the best interpretation of this​ result?     A.   The departmental manager was pleased with the efficiency of working and favoured all employees with a rise in wage rates.     B.   The employees worked inefficiently and so their wages were reduced to match the cost of the lost efficiency.     C.   The employees were...
If more direct materials were used than expected at standard: 1)The direct materials efficiency variance would...
If more direct materials were used than expected at standard: 1)The direct materials efficiency variance would be favourable 2)The direct labour efficiency variance would be unfavourable 3)The direct materials price variance would be favourable 4) The direct materials efficiency variance would be unfavourable
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required...
Pointe Claire Company applies overhead based on direct labour hours. Two direct labour hours are required for each unit of product. Planned production for the period was set at 8,300 units. Manufacturing overhead is budgeted at $124,500 for the period (20% of this cost is fixed). The 16,290 hours worked during the period resulted in the production of 8,000 units. The variable manufacturing overhead cost incurred was $100,800 and the fixed manufacturing overhead cost was $28,400. Calculate the variable overhead...
8. What does a favourable direct materials price variance indicate? a. The actual cost of materials...
8. What does a favourable direct materials price variance indicate? a. The actual cost of materials purchased was greater than the standard cost of materials purchased. b. The standard cost of materials purchased was less than the actual cost of materials purchased. c. The standard cost of materials purchased was greater than the actual cost of materials purchased. d. The actual quantity of materials used was less than the standard quantity of materials used for actual production. 9. In flexible...
Hollywood Jewellers planned to produce 1,800 necklaces during March with a total overhead budget of $49,600....
Hollywood Jewellers planned to produce 1,800 necklaces during March with a total overhead budget of $49,600. However, while manufacturing the 2,000th necklace the microcomputer that contained the month's cost information broke down. With the computer out of commission, the company has asked you to complete the variance analysis report. The missing information of the report is lettered in the following set of data: Variable overhead: Standard cost per necklace: 0.4 labour hour at $8 per hour Actual costs: $8,400 for...
McKenna Company planned to produce 900 units during April with a total overhead budget of $12,400.  ...
McKenna Company planned to produce 900 units during April with a total overhead budget of $12,400.   However, while manufacturing the 1,000 units the microcomputer that contained the month's cost information broke down. With the computer out of commission, the accountant has been unable to complete the variance analysis report. The information missing from the report is lettered in the following set of data: Variable overhead: Standard cost per unit: 0.4 labour hour at $4 per hour Actual costs: $2,100 for...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one...
Aaha Inc. produces premium protective automotive covers. The direct materials and direct labour standards for one car cover are as follows: Standard Quantity or Hours Standard Price or Rate Standard Cost   Direct materials 9.0 metres of cloth $ 10 per metre $ 90.00   Direct labour 0 hours $ 20 per hour $ 7   Variable overhead 0 hours $ 8 per hour $ 3 Budgeted fixed overhead cost is $17,400, and the normal production volume is 2,885 car covers. Overhead is...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to...
Direct labour variances and overhead spending variance The following data for Kitchen Tile Company relates to the production of 18 000 tiles during the past month. The entity allocates fixed overhead costs at a standard rate of $19 per direct labour hour. Direct Labour: Standard cost is 6 tiles per hour at $24 per hour Actual cost per hour was $24.50 Labour efficiency variance was $6720 F Fixed overhead costs: Estimated = $60,000 Actual = $58,720 Required (a)    How many...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT