A company expected its annual overhead costs to be $1,892,632 and direct labor costs to be $1,802,528. Actual overhead was $1,981,535, and actual labor costs totaled $1,294,067. How much is the company’s predetermined overhead rate to the nearest cent?
QUESTION:-A company expected its annual overhead costs to be $1,892,632 and direct labor costs to be $1,802,528. Actual overhead was $1,981,535, and actual labor costs totaled $1,294,067. How much is the company’s predetermined overhead rate to the nearest cent?
SOLUTIONS:-
As we are given with the following elements of a company:-
Annual overhead costs = $1,892,632 ,
Annual Direct labor costs =$1,802,528,
Actual overhead costs = $1,981,535,
and Actual labor costs = $1,294,067
REQUIREMENT:-.
The company’s predetermined overhead rate to the nearest cent = ?
the formula for predetermined overhead rate
= (ANNUAL OVERHEAD COST/ ANNUAL DIRECT LABOUR COST)*100
On putting the given values in the above formula, we get
= ($1,892,632/$1,802,528)*100
=104.9988%
So, the company’s predetermined overhead rate to the nearest cent = 105%