Question

Do you agree that if the difference between the Construction in Process and the Billings on...

Do you agree that if the difference between the Construction in Process and the Billings on Construction in Process account balances is a debit, the difference is reported as a current asset, why and why not?

Homework Answers

Answer #1

The balances of progress billings and construction in process should be shown at net, as a current asset if a debit balance, and as a current liability if a credit balance.

Under the completed contract method, the Construction in Process account balance consists of construction costs only.

The principal advantage of the completed-contract method is that reported revenue reflects final results rather than estimates.

Further, the amount of construction in progress which has not yet been collected ( unbilled) will be recovered later and hence should be classified as an asset.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Some investors believe the VIX follows a mean-reversion process. Do you agree? Why
Some investors believe the VIX follows a mean-reversion process. Do you agree? Why
Do you agree that "The odds of a failure within a six sigma process are 3.4...
Do you agree that "The odds of a failure within a six sigma process are 3.4 in a million"? Explain
Do you agree with this statement?   “Trade between individuals, tribes, and then nations has occurred for...
Do you agree with this statement?   “Trade between individuals, tribes, and then nations has occurred for thousands of years. Throughout the centuries, the desire to control trade and trade routes has often been the cause of conflict between countries. Why or why not?
The board of directors of Ogle Construction Company is meeting to choose between the completed contract...
The board of directors of Ogle Construction Company is meeting to choose between the completed contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Ogle's controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: 1. Ogle commenced doing business on January 1, 2018. 2. Construction activities for the year ended December 31, 2018, were...
Describe the difference between current and long-term assets and liabilities. Why do you think it is...
Describe the difference between current and long-term assets and liabilities. Why do you think it is important for assets and liabilities to be distinguished in terms of current and long-term?
how do you account for the difference in acidity between meta and para methoxyphenol?
how do you account for the difference in acidity between meta and para methoxyphenol?
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Carla Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Correct answer iconYour answer is correct. Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized...
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method...
The board of directors for Apache Construction Corp. is meeting to choose between the completed-contract method and the percentage-of-completion method of accounting for long-term contracts in the company's financial statements. You have been engaged to assist Apache’s controller in the preparation of a presentation to be given at the board meeting. The controller provides you with the following information: ·        Apache commenced doing business on January 1, 2020. ·        Construction activities for the year ended December 31, 2020, were as follows: Project...
What is the difference between these 4 types of businesses? Do you feel there is a...
What is the difference between these 4 types of businesses? Do you feel there is a difference between non-profit business and social business? If so, what? If not, why? How do each of these types of businesses impact the economy?
Do you agree with the following statement: Gross National Product (GNP) is the sum of Gross...
Do you agree with the following statement: Gross National Product (GNP) is the sum of Gross Domestic Product (GDP) and the current account (CA)? Provide a brief explanation.