Do you agree that if the difference between the Construction in Process and the Billings on Construction in Process account balances is a debit, the difference is reported as a current asset, why and why not?
The balances of progress billings and construction in process should be shown at net, as a current asset if a debit balance, and as a current liability if a credit balance.
Under the completed contract method, the Construction in Process account balance consists of construction costs only.
The principal advantage of the completed-contract method is that reported revenue reflects final results rather than estimates.
Further, the amount of construction in progress which has not yet been collected ( unbilled) will be recovered later and hence should be classified as an asset.
Get Answers For Free
Most questions answered within 1 hours.