Company manufactures one product. Its variable manufacturing overhead is applied to production based on direct labor-hours and its standard cost card per unit is as follows:
Direct materials: 5 pounds at $10 per pound | $ | 50 |
Direct labor: 4 hours at $16 per hour | 64 | |
Variable overhead: 4 hours at $7 per hour | 28 | |
Total standard cost per unit | $ | 142 |
The planning budget for March was based on producing and selling 20,000 units. However, during March the company actually produced and sold 24,600 units and incurred the following costs:
a.Purchased 164,000 pounds of raw materials at a cost of $7.50 per pound. All of this material was used in production.
b.Direct laborers worked 57,000 hours at a rate of $17 per hour.
c.Total variable manufacturing overhead for the month was $653,220.
If Preble had purchased 172,000 pounds of materials at $7.50 per pound and used 164,000 pounds in production, what would be the materials price variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.)
If Preble had purchased 172,000 pounds of materials at $7.50 per pound and used 164,000 pounds in production, what would be the materials quantity variance for March? (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance.). Input all amounts as positive values.)
What direct labor cost would be included in the company’s planning budget for March?
What direct labor cost would be included in the company’s flexible budget for March?
1.
Material price variance = (Actual price - Standard price) * Actual quantity purchased
Material price variance = ($7.50 - $10) * 172,000 = $430,000 Favorable
2.
Material quantity variance = (Standard quantity - Actual quantity used) * Standard price
Material quantity variance = (24,600*5 - 164,000) * $10
Material quantity variance = (123,000 - 164,000) * $10 = $410,000 Unfavorable
3.
Direct labor cost included in planning budget = 20,000 * $64 = $1,280,000
4.
Direct labor cost included in flexible budget = 24,600 * $64 = $1,574,400