Manufacturing Overhead Distribution Worksheet The following are selected operating data for the production and service departments...

Manufacturing Overhead Distribution Worksheet

The following are selected operating data for the production and service departments of Bluestone Company for 2016.

Departments
Service Production
1 2 1 2
Overhead costs (identified by department)
Indirect material $72,600 $123,300 $38,160 $774,000
Indirect labor $145,800 $216,000 $48,876 $2,158,500
Square feet of building floor space used 7,200 10,800 18,000 36,000
Assessed value of equipment used $31,500 $94,500 $189,000 $315,000
Cubic yards of factory space used 132,000 198,000
Machine hours 76,800 307,200
Direct labor $30,000 $600,000

Building depreciation of $144,000 is allocated on the basis of square feet of floor space. Personal property taxes of $54,000 are allocated on the basis of assessed values of equipment used. Costs for service departments 1 and 2 are allocated to production departments on the basis of cubic yards of factory space and machine hours, respectively.

Required

a. Prepare a 2016 overhead distribution worksheet for Bluestone Company similar to the one prepared for Exhibit 3-15.

Use negative signs with answers, when appropriate. Under the Allocation Basis column, select the basis used to calculate each allocation.

Bluestone Company
Overhead Distribution Worsksheet
For the Year Ended December 31, 2016

Service

Dept. 1 Dept. 2

Production

Dept. 1 Dept. 2

Allocation Basis
Directly identifiable with departments:
Indirect material Answer Answer Answer Answer
Indirect labor Answer Answer Answer Answer
Allocated to departments:
Building depreciation Answer Answer Answer Answer AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
Personal property taxes Answer Answer Answer Answer AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
Total overhead Answer Answer Answer Answer
Allocation of service departments:
Dept. 1 Answer Answer Answer Answer AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
Dept. 2 Answer Answer Answer Answer AnswerAssessed value of equipmentCubic yards of factory spaceFloor spaceMachine hours used
Total allocated overhead Answer Answer Answer Answer

b. Compute the manufacturing overhead rates for production departments 1 and 2 using machine hours and direct labor costs, respectively, for allocation bases.

Round answers to two decimal places, when applicable.

Production Dept. 1 Answer
Production Dept. 2 Answer

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
The following is taken from Clausen Company’s internal records of its factory with two operating departments....
The following is taken from Clausen Company’s internal records of its factory with two operating departments. The cost driver for indirect labor is direct labor hours, and the cost driver for the remaining items is number of hours of machine use. Compute the total amount of overhead allocated to Dept. 2 using activity-based costing. Direct Labor Hours Machine Hours Operating Dept. 1 1,410 11,160 Operating Dept. 2 3,290 7,440 Totals 4,700 18,600 Factory overhead costs Rent and utilities $ 26,800...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and packaging. Information for the three service departments is given below: Admin Maint Person Directly traced overhead $69,000 $45,000 $78,000 Square feet occupied 2,000 3,500 3,000 Number of employees 36 24 30 Maintenance hours 2,500 2,000 4,000 Information for the two production departments is given below: Assembly Packaging Directly traced overhead $167,040 $122,090 Square feet occupied 2,100 1,400 Number of employees 42 18 Maintenance hours...
Consider the following information: Service Dept 1 Service Dept 2 Production Dept 1 Production Dept 2...
Consider the following information: Service Dept 1 Service Dept 2 Production Dept 1 Production Dept 2 Costs $200,000 $150,000 $450,000 $480,000 Allocation base: SF (for Service 1) 2,000 2,500 20,000 30,000 LH (for service 2) 15,000 16,000 40,000 40,000 Under the direct method of allocating service department costs, how much (in dollars) of Service Dept 1’s costs should be allocated to Production Department 2? (Service Dept 1 costs are allocated on the basis of square feet (SF). Service Dept 2...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and packaging. Information for the three service departments is given below: Admin Maint Person Directly traced overhead $65,000 $33,000 $74,000 Square feet occupied 2,000 3,500 3,000 Number of employees 42 24 30 Maintenance hours 2,500 2,000 4,000 Information for the two production departments is given below: Assembly Packaging Directly traced overhead $167,030 $114,090 Square feet occupied 2,100 1,400 Number of employees 36 18 Maintenance hours...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and...
Av-Y6 Company operates three service departments, administration, maintenance, and personnel and two production departments, assembly and packaging. Information for the three service departments is given below: Admin Maint Person Directly traced overhead $69,000 $45,000 $78,000 Square feet occupied 2,000 3,500 3,000 Number of employees 36 24 30 Maintenance hours 2,500 2,000 4,000 Information for the two production departments is given below: Assembly Packaging Directly traced overhead $167,040 $122,090 Square feet occupied 2,100 1,400 Number of employees 42 18 Maintenance hours...
Anderson Enterprises has three service departments, Administration, Maintenance and security and two production departments, Machining and...
Anderson Enterprises has three service departments, Administration, Maintenance and security and two production departments, Machining and Assembly. Total Manufacturing overhead was either directly traced or allocated to all of the departments resulting gin a total of $300,000 of overhead in the Maintenance Department, $240,000 in the administration department, $135,000 in the security department, $1,000,000 in the machining department and $300,000 in the assembly department. The company allocates service department cost using the step method. The maintenance department overhead is allocated...
Caro Manufacturing has two production departments, Machining and Assembly, and two service departments, Maintenance and Cafeteria....
Caro Manufacturing has two production departments, Machining and Assembly, and two service departments, Maintenance and Cafeteria. Direct costs for each department and the proportion of service costs used by the various departments for the month of August follow: Proportion of Services Used by Department Direct Costs Maintenance Cafeteria Machining Assembly Machining $ 104,000 Assembly 74,400 Maintenance 46,000 — 0.2 0.5 0.3 Cafeteria 37,000 0.6 — 0.2 0.2 Assume that both Machining and Assembly work on just two jobs during the...
The building maintenance department for the Steering Manufacturing Company budgets annual costs of $5,402,000 based on...
The building maintenance department for the Steering Manufacturing Company budgets annual costs of $5,402,000 based on the expected operating level for the coming year. The costs are allocated to two production departments. Steering is considering two allocation bases for assignment of costs to departments: (1) square footage and (2) direct labor hours. The following data relate to the potential allocation bases: Production Dept. 1 Production Dept. 2 Square footage 31,660 41,340 Direct labor hours 41,340 31,660 Calculate the costs allocated...
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing)....
University Printers has two service departments (Maintenance and Personnel) and two operating departments (Printing and Developing). Management has decided to allocate maintenance costs on the basis of machine-hours in each department and personnel costs on the basis of labor-hours worked by the employees in each. The following data appear in the company records for the current period: Maintenance Personnel Printing Developing Machine-hours — 1,700 1,700 5,100 Labor-hours 700 — 700 2,800 Department direct costs $ 2,400 $ 12,400 $ 14,100...
Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly Finishing Manufacturing overhead...
Rafner Manufacturing identified the following budgeted data in its two production departments. Assembly Finishing Manufacturing overhead costs $ 1,120,800 $ 510,000 Direct labor hours 11,100 DLH 19,100 DLH Machine hours 5,100 MH 15,100 MH 1. What is the company's single overhead rate based on direct labor hours? Estimated overhead costs       per direct labor hour Estimated direct labor hours 2. What is the company's single plantwide overhead rate base on machine hours? Estimated overhead costs per machine hour Estimated...